Hi
We are about to install ply shuttering for residential footings.
Is it normal practice NOT to back fill once the shuttering is in place.
We would like to remove the ply (10 8' x 4' sheets (cut of course))
after the concrete has cured.
Although the 18mm ply is braced - we were thinking of inserting
stakes from the
surrounding bank and wedged on to the shuttering.
Have you had this allowed before by BI's.
Or do you think the BI will want the ply trench to be back filled?
I ask because we do not want to dig it all out again to recover the ply!
Thanks in advance.
Stephen
We are about to install ply shuttering for residential footings.
Is it normal practice NOT to back fill once the shuttering is in place.
We would like to remove the ply (10 8' x 4' sheets (cut of course))
after the concrete has cured.
Although the 18mm ply is braced - we were thinking of inserting
stakes from the
surrounding bank and wedged on to the shuttering.
Have you had this allowed before by BI's.
Or do you think the BI will want the ply trench to be back filled?
I ask because we do not want to dig it all out again to recover the ply!
Thanks in advance.
Stephen