Hi
Would anyone be able to check my logic for the next steps of getting my extension out of the ground? The foundations are now poured to 450mm below damp.
- I was planning on laying one course of blocks (to get within 225mm of dpc) then filling the cavity with lean mix concrete then running the trowel along it to slope it towards the outer skin? Then laying the rest up to dpc.
- back filling after getting to dpc I was planning on using a mix of soil and hardcore, but have heard that you shouldn't use soil, any opinions appreciated!
Would anyone be able to check my logic for the next steps of getting my extension out of the ground? The foundations are now poured to 450mm below damp.
- I was planning on laying one course of blocks (to get within 225mm of dpc) then filling the cavity with lean mix concrete then running the trowel along it to slope it towards the outer skin? Then laying the rest up to dpc.
- back filling after getting to dpc I was planning on using a mix of soil and hardcore, but have heard that you shouldn't use soil, any opinions appreciated!