W
walkern
He'll,
Need a bit of advice. I'm building a porch (well doing some of the donkey work to save money). I've gone down 900mm, but about 20cm from the bottom the electric cable runs thought it perpendicular at the front of what will be the porch.
My builder friend says dig a few extra inches down, about a foot wide, around the cable, get the concrete people to fill the whole trench to just below the pipe, then shutter an inch to each side and continue filling. Then fill the gap with sand and the bricks will bridge over the top.
This means my foundations are in two pieces essentially. Would it not be better to somehow cover the top of the pipe and then fill it all? Or am I over thinking this as a problem...
Thanks.
Need a bit of advice. I'm building a porch (well doing some of the donkey work to save money). I've gone down 900mm, but about 20cm from the bottom the electric cable runs thought it perpendicular at the front of what will be the porch.
My builder friend says dig a few extra inches down, about a foot wide, around the cable, get the concrete people to fill the whole trench to just below the pipe, then shutter an inch to each side and continue filling. Then fill the gap with sand and the bricks will bridge over the top.
This means my foundations are in two pieces essentially. Would it not be better to somehow cover the top of the pipe and then fill it all? Or am I over thinking this as a problem...
Thanks.