Hi - we have had plans approved by the LA for a loft conversion and dormer. The plans are fine at the guy i used provided structural calcs and a detailed specification - this was all completed a little while ago.
We are now in the process on requesting quotes and some builders we have spoken to have made some valid and useful suggestions. If we take these on board it would it mean we would deviate from the approved plans and specification.
Generally, is there scope of deviate from the details previously submited to the council?
The sort of changes may include:
- moving a door way in a non-structural stud wall
- use of a thinner insulation material - increasing headroom
I would like to assume that so long as the structural work is completed to spec/plans, then BC will be happy so long as the other work conforms to regs - i.e., correct u values on insulation, etc.
advice appreciated
Phil
We are now in the process on requesting quotes and some builders we have spoken to have made some valid and useful suggestions. If we take these on board it would it mean we would deviate from the approved plans and specification.
Generally, is there scope of deviate from the details previously submited to the council?
The sort of changes may include:
- moving a door way in a non-structural stud wall
- use of a thinner insulation material - increasing headroom
I would like to assume that so long as the structural work is completed to spec/plans, then BC will be happy so long as the other work conforms to regs - i.e., correct u values on insulation, etc.
advice appreciated
Phil