Isn't hindsight a great thing?!
I'd be very grateful for anyones thoughts and/or experiences on the situation I fear we may have got ourselves in to.
Background: In September 2016 we purchased a 3 bed 1930s detached house which we have been renovating. We always intended to stay in it for a long time and as such intended also to extend it - we applied for, and successfully got planning permission in December 2017 to extend to a 5 bed including loft conversion. For me, the planning permission was obvious, as (so I thought) were BC and regs for the extension. Never would have I thought that I would need BC involvement for renovating! I have always been a very confident (and I think) capable DIY'er - I used to work in a very niche area of data and alarm installations but never in domestic scenarios or at any time really when I would have to consider things like building regs.
Fast forward to now, and my wife is less than a week away from due date for our first child, we have moved out of the above property to one that we used to let but is in her home town so that she can be near family (she was feeling isolated where we were) and I now need to get the above property in to a state that we can sell it, which is where the worry is starting to set in. We have had some BC involvement when I started to realise how things might be affected - therefore we do have an open regularisation application for the loft conversion which I'll explain further down.
If I may, I'll list where I think BC may apply and what I know of where we are up to:
The biggest concern is the regularisation certificate for the loft conversion. When we took the ceilings down, we thought it would be a good idea to install the new joists, a steel and a couple of flitch beams associated with the loft conversion whilst everything was open. The only structural change at the moment really is the removal of one of the stair containing walls (both containing walls supported the roof purlins) and loading transferred to a steel contained within a partition wall which splits an existing bedroom in to a landing, bedroom and bathroom. The new plasterboard for the ceiling was then fixed to the new joists which are installed to structural engineers specifications. He wasn't actually that concerned about the loading on the steel at the moment as theres still the existing containing wall supporting the purlins and actually, the old 1930s timbers cross bracing on to the walls were only 75mm and notched on to the purlins!
It was at this point that I started to realise that I should have spoken to BC, which I then did. The BCO visited at the point where everything was still open and was happy with the workmanship (all installed by a local carpenter). She knew of the structural engineer and commented that he usually over specced and she was unaware of there having ever been any problems with his calculations or designs so was happy with those too (but still asked me to send all the designs through). I completed the regularisation application form and paid the fee and we agreed that we would speak again when starting work on the loft conversion and extension properly, subject at that point to planning permission.
So this is now the problem - we have a 'non-compliant work' open file against the property which we basically cannot have completed/closed without actually doing the loft conversion and extension! It feels like this will come back to bite me when searches start to happen, but notified or not, I think we would probably be in the same position?
Does anyone have any ideas on whether my assumptions of where we are with all the bits of work feels accurate and how we may be able to approach the conundrum of the open regularisation application? Can I cancel it and reapply as a structural change or something?
Sorry this has been a waffle but any thoughts very much appreciated.
John
I'd be very grateful for anyones thoughts and/or experiences on the situation I fear we may have got ourselves in to.
Background: In September 2016 we purchased a 3 bed 1930s detached house which we have been renovating. We always intended to stay in it for a long time and as such intended also to extend it - we applied for, and successfully got planning permission in December 2017 to extend to a 5 bed including loft conversion. For me, the planning permission was obvious, as (so I thought) were BC and regs for the extension. Never would have I thought that I would need BC involvement for renovating! I have always been a very confident (and I think) capable DIY'er - I used to work in a very niche area of data and alarm installations but never in domestic scenarios or at any time really when I would have to consider things like building regs.
Fast forward to now, and my wife is less than a week away from due date for our first child, we have moved out of the above property to one that we used to let but is in her home town so that she can be near family (she was feeling isolated where we were) and I now need to get the above property in to a state that we can sell it, which is where the worry is starting to set in. We have had some BC involvement when I started to realise how things might be affected - therefore we do have an open regularisation application for the loft conversion which I'll explain further down.
If I may, I'll list where I think BC may apply and what I know of where we are up to:
- Removal of all plaster to exterior walls and boarded/skimmed - Req to upgrade thermal elements - achieved through installation of cavity wall insulation (through certified company).
- Removal and replacement of cavity floor covering - Req to upgrade thermal elements - achieved by 75mm (maximum achievable) Celotex between joists, foam and foil tape, 22mm egger board - seen in progress by BCO who said the job looked very good! But certificate required?
- Replacement of lath+plaster ceilings and replaced with skimmed 12.5mm plaster board - req to upgrade thermal element - 300ish mm of rock wool installed - notifiable work?
- Log burner - installation by HETAS certified company.
- New front door - installation by FENSA certified company (uPVC windows already installed when we purchased)
- Rewire - Installation by Part P registered electrician.
- Relocated and new boiler - installation by registered gas safe plumber
- New bathroom upstairs in split existing bedroom - all pipework installed by same plumber - assumed registered as competent person and NFA required?
- New soil pipe to existing property drain - installed by local drainage company - assumed registered as competent person and NFA required?
- Ventilation - Cooker extractor hood and bathroom over shower extractor - neither require notification as considered minor works under Part F?
- New banisters on existing stair case - Installed by local chippy but gap between spindles is approx 105-110mm at its maximum - notifiable work?
- New partition wall between bedroom and bathroom - filled with rockwool for sound isolation - notifiable work?
The biggest concern is the regularisation certificate for the loft conversion. When we took the ceilings down, we thought it would be a good idea to install the new joists, a steel and a couple of flitch beams associated with the loft conversion whilst everything was open. The only structural change at the moment really is the removal of one of the stair containing walls (both containing walls supported the roof purlins) and loading transferred to a steel contained within a partition wall which splits an existing bedroom in to a landing, bedroom and bathroom. The new plasterboard for the ceiling was then fixed to the new joists which are installed to structural engineers specifications. He wasn't actually that concerned about the loading on the steel at the moment as theres still the existing containing wall supporting the purlins and actually, the old 1930s timbers cross bracing on to the walls were only 75mm and notched on to the purlins!
It was at this point that I started to realise that I should have spoken to BC, which I then did. The BCO visited at the point where everything was still open and was happy with the workmanship (all installed by a local carpenter). She knew of the structural engineer and commented that he usually over specced and she was unaware of there having ever been any problems with his calculations or designs so was happy with those too (but still asked me to send all the designs through). I completed the regularisation application form and paid the fee and we agreed that we would speak again when starting work on the loft conversion and extension properly, subject at that point to planning permission.
So this is now the problem - we have a 'non-compliant work' open file against the property which we basically cannot have completed/closed without actually doing the loft conversion and extension! It feels like this will come back to bite me when searches start to happen, but notified or not, I think we would probably be in the same position?
Does anyone have any ideas on whether my assumptions of where we are with all the bits of work feels accurate and how we may be able to approach the conundrum of the open regularisation application? Can I cancel it and reapply as a structural change or something?
Sorry this has been a waffle but any thoughts very much appreciated.
John