Hi,
Due to an extension the cold water into the house comes up in the middle of the kitchen floor. This was done in a previous extension, now uncovered for the further extension. The water in was extended to wall in copper (I think there might have been a bit of plastic pipe of that). This was buried in the screed and tiled over. Where the blue water pipe covers up is a bit of soil pipe (110mm) around it.
I want to replace this and take it further. I plan to use 22mm pex pipe joined to blue pipe. I'm thinking 25mm flex conduit around the pex so I can have bends, i.e. only one joint. How deep do I need to go with this? Screed is ~50mm so I'd have about 25mm over the conduit. I wonder if I should groove the slab (15mm?) so I get more depth of screed> Maybe add fibres to screed?. I also plan to cut the screed back so as to have say a 150mm wide section I'm re-screeding with the pipe in the middle. Effectively forming a bridge over the conduit (I'm expecting the conduit to flex so load above it needs to transfer to either side.
Comments?
Not sure what to cover over the soil pipe end where the blue water pipe exits.
I did think about letting in some chipboard floor (supporting 50mm each side with screed), but I'm going to tile over it in the end any way so if there are problems then digging out screed is less of an issue than taking up tiles and repairing. Also screed to chipboard (or OSB3) sounds likely to move so an issue for tiling over.
Due to an extension the cold water into the house comes up in the middle of the kitchen floor. This was done in a previous extension, now uncovered for the further extension. The water in was extended to wall in copper (I think there might have been a bit of plastic pipe of that). This was buried in the screed and tiled over. Where the blue water pipe covers up is a bit of soil pipe (110mm) around it.
I want to replace this and take it further. I plan to use 22mm pex pipe joined to blue pipe. I'm thinking 25mm flex conduit around the pex so I can have bends, i.e. only one joint. How deep do I need to go with this? Screed is ~50mm so I'd have about 25mm over the conduit. I wonder if I should groove the slab (15mm?) so I get more depth of screed> Maybe add fibres to screed?. I also plan to cut the screed back so as to have say a 150mm wide section I'm re-screeding with the pipe in the middle. Effectively forming a bridge over the conduit (I'm expecting the conduit to flex so load above it needs to transfer to either side.
Comments?
Not sure what to cover over the soil pipe end where the blue water pipe exits.
I did think about letting in some chipboard floor (supporting 50mm each side with screed), but I'm going to tile over it in the end any way so if there are problems then digging out screed is less of an issue than taking up tiles and repairing. Also screed to chipboard (or OSB3) sounds likely to move so an issue for tiling over.