Hi, Could do with some guidance if anyone is able to help please!
I am planning on installing the rads & pipework myself (to save on some costs) - Property is a chalet bungalow.
I've done a few diagrams but this one seems to make sense (but not sure if correct).
Followed some websites guidance with the reverse return method to make all circuits similar resistance.
Intended combi boiler would be 30kW
Flow and return pipes would be 22mm (pb plastic)
drops/pipework to rads 15mm (pb plastic / copper)
all 8 rads total about 8kW (5-6 rads on TRV's)
1 zone system for both ground floor and 1st floor (orange rads are ground floor, big greens are first floor bedrooms, little green is 1st floor bathroom).
Would this be the correct way to go about it? As this plan avoids the need to plumb pipes through joists (joists are running left to right), so most of the pipework is running above joists along the internal side of the eaves (i.e. service void or back of dwarf wall)
Thanks for any help
attached a blank plan if you have any better suggestions cheers
I am planning on installing the rads & pipework myself (to save on some costs) - Property is a chalet bungalow.
I've done a few diagrams but this one seems to make sense (but not sure if correct).
Followed some websites guidance with the reverse return method to make all circuits similar resistance.
Intended combi boiler would be 30kW
Flow and return pipes would be 22mm (pb plastic)
drops/pipework to rads 15mm (pb plastic / copper)
all 8 rads total about 8kW (5-6 rads on TRV's)
1 zone system for both ground floor and 1st floor (orange rads are ground floor, big greens are first floor bedrooms, little green is 1st floor bathroom).
Would this be the correct way to go about it? As this plan avoids the need to plumb pipes through joists (joists are running left to right), so most of the pipework is running above joists along the internal side of the eaves (i.e. service void or back of dwarf wall)
Thanks for any help
attached a blank plan if you have any better suggestions cheers