Hi guys,
Thanks for your time.
Currently having a kitchen extension built 6m x 4m. Builder just recently poured the concrete slab. Before he did building control passed the insulation etc and away they went. As far as I was aware the usual process is 4" concrete with steel followed by 2" screed however my builder poured 2" concrete (Ontop of 100mm Celotex and waterproof membrane) from a concrete wagon and mixed the second 2" himself using sharp sand and cement and added this ontop of the 2" of poured concrete, he said he kept the concrete wet all day while he added the cement and sharp sand and added steel at 2". He says this will save money on adding a floor screed at a later date to further level the floor as he's gotten it pretty level already.
Is this an acceptable process do you feel? He says as it was all done in one day and the concrete was kept wet it will have cured as a 4" slab?
Any opinions would be appreciated.
Thanks.
Thanks for your time.
Currently having a kitchen extension built 6m x 4m. Builder just recently poured the concrete slab. Before he did building control passed the insulation etc and away they went. As far as I was aware the usual process is 4" concrete with steel followed by 2" screed however my builder poured 2" concrete (Ontop of 100mm Celotex and waterproof membrane) from a concrete wagon and mixed the second 2" himself using sharp sand and cement and added this ontop of the 2" of poured concrete, he said he kept the concrete wet all day while he added the cement and sharp sand and added steel at 2". He says this will save money on adding a floor screed at a later date to further level the floor as he's gotten it pretty level already.
Is this an acceptable process do you feel? He says as it was all done in one day and the concrete was kept wet it will have cured as a 4" slab?
Any opinions would be appreciated.
Thanks.