Hello all,
We've had the house extended, it's been a built a few years now, all decorated, carpet laid, bath in, floor tiled etc. At the time it was built I commented to the architect that the floor seemed springy but he remarked the joists were the correct size but the build was definitely to "a budget" without elaborating what was wrong or what could be better. He suggested noggins were added, so they were (you can see them in the later pictures).
View media item 84562View media item 84563View media item 84564
We have chipboard T&G which I initially unhappy about, In hindsight we should have gone for proper flooring boards. Though I think we'd still behaving the same problem, that is to say: the entire flooring in this room seems a little springy and because of this overall movement the T&G boarding is beginning to work loose and creaks every step of the way for half the room.
The joists run perpendicular to those in the original part of the house, as downstairs is the garage so there can be no internal supporting wall.
View media item 84544View media item 84545View media item 84546View media item 84547View media item 84548View media item 84549View media item 84550View media item 84551View media item 84552View media item 84553
What I want to do is pull up the T&G chipboard, somehow reinforce/strengthen the existing joist, then relay with proper wood flooring boards. That "somehow" is what I'm posting about really.
There are a number of snags I'll need to work through, or questions I'm seeking advice on:
Pulling up existing floor:
Large sheets, some of which have a stud wall nailed through them - how best to remove sheets with minimal damage to stud walls? Also to consider pipes and cables that are thread through chipboard - I must drill, cut or use some blunt pulling/stabbing instrument to remove the chipboard..
View media item 84557View media item 84558View media item 84559View media item 84560View media item 84561
Reinforcing the joists:
a) Add a/some steels?
b) Add some strapping?
View media item 84554c) Add more noggins?
d) Double up joist?
e) joist hangers?
f) best way to bed them on top of aircrete on one end, brick on the other.
g) Any solution needs to be suited for routing for existing cables/pipes.
h) Any other solutions? Concrete beams? Lifting tackles? Cable/pipe management?
View media item 84555
I'll be getting in a builder in for this reinforcing part of the project as I don't have the skills nor contacts, but I want to understand all the options out there so I can reject what isn't going to work or be inadequate.
Replacing floorboards
Best way to re-attach stud walls to the floorboards? (I think screw from the underside using a 90degree drill adaptor, whilst avoiding pipes & cables).
How best to make the transition from old flooring, across concrete "filler" above adjoining brick wall (photo xxxx.jpg) into the new boarding such that the hump doesn't show through the carpet as it currently does. May involve grinding/cutting back concrete with disc then bedding down some hardboard to the same level or having the new board extending over this to be affixed to the old joists (that run perpendicular)
View media item 84556
Some of the old boarding is currently supporting the bath and tiled bathroom, and this must stay undisturbed - I think it is the weight of this stuff and the shape of the partition is the reason why only half of the room creaks/bends rather than all of it.
Should I get an architect/architectural technician or structural engineer to size up the job or will that just add cost be no real benefit? What should I consider w.r.t building regs? The underside is already fire protected (i.e. garage ceiling is already fireline boarding one orientation, plasterboard the other)
I think this job is easier to manage "from above" as if I do it from the garage I have to take all the strips lights down, the ceiling (fireboard and plasterboard) the boxing-in of the soil pipe and take all the insulation out too). Though the advantage is I can see where all the cables and pipes are.
Nozzle
We've had the house extended, it's been a built a few years now, all decorated, carpet laid, bath in, floor tiled etc. At the time it was built I commented to the architect that the floor seemed springy but he remarked the joists were the correct size but the build was definitely to "a budget" without elaborating what was wrong or what could be better. He suggested noggins were added, so they were (you can see them in the later pictures).
View media item 84562View media item 84563View media item 84564
We have chipboard T&G which I initially unhappy about, In hindsight we should have gone for proper flooring boards. Though I think we'd still behaving the same problem, that is to say: the entire flooring in this room seems a little springy and because of this overall movement the T&G boarding is beginning to work loose and creaks every step of the way for half the room.
The joists run perpendicular to those in the original part of the house, as downstairs is the garage so there can be no internal supporting wall.
View media item 84544View media item 84545View media item 84546View media item 84547View media item 84548View media item 84549View media item 84550View media item 84551View media item 84552View media item 84553
What I want to do is pull up the T&G chipboard, somehow reinforce/strengthen the existing joist, then relay with proper wood flooring boards. That "somehow" is what I'm posting about really.
There are a number of snags I'll need to work through, or questions I'm seeking advice on:
Pulling up existing floor:
Large sheets, some of which have a stud wall nailed through them - how best to remove sheets with minimal damage to stud walls? Also to consider pipes and cables that are thread through chipboard - I must drill, cut or use some blunt pulling/stabbing instrument to remove the chipboard..
View media item 84557View media item 84558View media item 84559View media item 84560View media item 84561
Reinforcing the joists:
a) Add a/some steels?
b) Add some strapping?
View media item 84554c) Add more noggins?
d) Double up joist?
e) joist hangers?
f) best way to bed them on top of aircrete on one end, brick on the other.
g) Any solution needs to be suited for routing for existing cables/pipes.
h) Any other solutions? Concrete beams? Lifting tackles? Cable/pipe management?
View media item 84555
I'll be getting in a builder in for this reinforcing part of the project as I don't have the skills nor contacts, but I want to understand all the options out there so I can reject what isn't going to work or be inadequate.
Replacing floorboards
Best way to re-attach stud walls to the floorboards? (I think screw from the underside using a 90degree drill adaptor, whilst avoiding pipes & cables).
How best to make the transition from old flooring, across concrete "filler" above adjoining brick wall (photo xxxx.jpg) into the new boarding such that the hump doesn't show through the carpet as it currently does. May involve grinding/cutting back concrete with disc then bedding down some hardboard to the same level or having the new board extending over this to be affixed to the old joists (that run perpendicular)
View media item 84556
Some of the old boarding is currently supporting the bath and tiled bathroom, and this must stay undisturbed - I think it is the weight of this stuff and the shape of the partition is the reason why only half of the room creaks/bends rather than all of it.
Should I get an architect/architectural technician or structural engineer to size up the job or will that just add cost be no real benefit? What should I consider w.r.t building regs? The underside is already fire protected (i.e. garage ceiling is already fireline boarding one orientation, plasterboard the other)
I think this job is easier to manage "from above" as if I do it from the garage I have to take all the strips lights down, the ceiling (fireboard and plasterboard) the boxing-in of the soil pipe and take all the insulation out too). Though the advantage is I can see where all the cables and pipes are.
Nozzle