Hi,
I have a recently built (2007) steel framed semi-detatched house.
I have gutted the upstairs ensuite bathroom (2.4m x 0.85m), partly to retile it and partly to fix a botched quasi-wetroom which had not been properly tanked.
The wetroom plumbing (trap, drain etc) is set into the reinforced concrete floor, with the waste pipe approx 3 or 4cm below the surface of the screed.
I need to relocate the shower trap about 8cm to the right (so its central to the shower enclosure), but I have encountered a couple of pieces of rebar.
This was my worst fear, as I am very uncomfortable about cutting through any sections of rebar for obvious reasons, but I was curious whether its possible to cut out a very small section (only about 25cm needs removing)?
Also, Is it possible to reposition and then weld the rebar 10cm further along its length to compensate for the section that was removed?
I have a recently built (2007) steel framed semi-detatched house.
I have gutted the upstairs ensuite bathroom (2.4m x 0.85m), partly to retile it and partly to fix a botched quasi-wetroom which had not been properly tanked.
The wetroom plumbing (trap, drain etc) is set into the reinforced concrete floor, with the waste pipe approx 3 or 4cm below the surface of the screed.
I need to relocate the shower trap about 8cm to the right (so its central to the shower enclosure), but I have encountered a couple of pieces of rebar.
This was my worst fear, as I am very uncomfortable about cutting through any sections of rebar for obvious reasons, but I was curious whether its possible to cut out a very small section (only about 25cm needs removing)?
Also, Is it possible to reposition and then weld the rebar 10cm further along its length to compensate for the section that was removed?