Evening all,
Was just wondering on how to integrate my DPM from my new extension (solid slab) in the existing house.
Clearly i'll be running the DPM over the footing wall at the current DPC level on the new externals but on the internal 'join' I have a bitumen paint under some parquet flooring (house is 1922).
I could take up the section of existing a bit and overlap the DPM say by 300mm or can i just cut it alone the internal join and then insulate and screed over the whole lot?
Thanks