- Joined
- 17 Dec 2018
- Messages
- 559
- Reaction score
- 15
- Country
I just wanted a second opinion on the payment schedule proposed by a builder for a loft conversion with Dormer Extension
Total cost of works - £44K
Duration 8-9 weeks
Deposit prior to work - £4K
Deposit by end of week 1 - £20K
Payment on completeion of main construction - £17
Final Payment of completion of works (i.e. plastering/2nd fix/electrics) - £3K
Materials and scaffolding arranged by builder
Total cost of works - £44K
Duration 8-9 weeks
Deposit prior to work - £4K
Deposit by end of week 1 - £20K
Payment on completeion of main construction - £17
Final Payment of completion of works (i.e. plastering/2nd fix/electrics) - £3K
Materials and scaffolding arranged by builder
Last edited: