We're looking to give our downstairs cloakroom an upgrade/makeover.
The existing sink will be removed as it never had a pedestal and will be replaced with a new one. We'll also get the toilet taken off and possibly replace with a new one (missus hasn't decided). Both of these will be done by a plumber. The new sink/toilet will also be installed by a plumber.
We're taking the plasterboard walls and ceiling off as well so we can install insulation between the partitions / above the ceiling.
We'll then add insulation between the studs and above the ceiling (there is none at the moment), and put up fresh plasterboard.
We're also tiling the wall to about 3 or 4 feet high on all 4 walls of the room, with a mirror cut to size from the top of the tiling to the ceiling, the mirror going on the wall on the left of the pic below and also onthe wall with the diagonal/slope where the stairwell cuts in).
Some Q's:-
1. For the sink, where the attachments to hold it to the wall will go, do we need to put wooden battens between the timber studs (prior to re sheeting the plasterboard and doing the tiling) so that the screws to hold the sink will be screwed into both tile and wood? Or would we be ok with wall anchors only?
2. Given that this room will have both a toilet and sink, what kind of acoustic mineral wool can be used / is suitable for use between the studs? Can we use high acoustic rated wool and if so is there a particular type that must be used in rooms with high humidity?
3. What type of plasterboard can be used? We'd prefer to use an acoustic type of plasterboard if possible, but again are we restricted due to the humidity levels in the room?
4. The walls at the moment don't have any tiling on them, neither behind where the existing sink is nor behind the existing toilet. We'll be installing tiling behind both the new sink and the new toilet, and in addition potentially thicker sheets of plasterboard, all of which will mean the new sink/toilet will be positioned slightly further into the room than they were before (and so farther away from the existing pipework than the existing sink/toilet are). Is it then a fairly straightforward job for the plumber to attach the new sink/toilet to the existing pipework, or are there issues caused by the new toilet /sink being further away from these connections than the old toilet/sink were?
The existing sink will be removed as it never had a pedestal and will be replaced with a new one. We'll also get the toilet taken off and possibly replace with a new one (missus hasn't decided). Both of these will be done by a plumber. The new sink/toilet will also be installed by a plumber.
We're taking the plasterboard walls and ceiling off as well so we can install insulation between the partitions / above the ceiling.
We'll then add insulation between the studs and above the ceiling (there is none at the moment), and put up fresh plasterboard.
We're also tiling the wall to about 3 or 4 feet high on all 4 walls of the room, with a mirror cut to size from the top of the tiling to the ceiling, the mirror going on the wall on the left of the pic below and also onthe wall with the diagonal/slope where the stairwell cuts in).
Some Q's:-
1. For the sink, where the attachments to hold it to the wall will go, do we need to put wooden battens between the timber studs (prior to re sheeting the plasterboard and doing the tiling) so that the screws to hold the sink will be screwed into both tile and wood? Or would we be ok with wall anchors only?
2. Given that this room will have both a toilet and sink, what kind of acoustic mineral wool can be used / is suitable for use between the studs? Can we use high acoustic rated wool and if so is there a particular type that must be used in rooms with high humidity?
3. What type of plasterboard can be used? We'd prefer to use an acoustic type of plasterboard if possible, but again are we restricted due to the humidity levels in the room?
4. The walls at the moment don't have any tiling on them, neither behind where the existing sink is nor behind the existing toilet. We'll be installing tiling behind both the new sink and the new toilet, and in addition potentially thicker sheets of plasterboard, all of which will mean the new sink/toilet will be positioned slightly further into the room than they were before (and so farther away from the existing pipework than the existing sink/toilet are). Is it then a fairly straightforward job for the plumber to attach the new sink/toilet to the existing pipework, or are there issues caused by the new toilet /sink being further away from these connections than the old toilet/sink were?
Attachments
Last edited: