Hi,
I'm just setting out the footings for my new extension. 6 feet away is a shed that I envisage will need power and maybe a network cable in a couple of years.
I'd like to lay an underground duct now to make things easier and neater in future (outside will be rendered) , and then when I'm having the extension electrics first fixed I can ask the electrician to push through some SWA for future use before everything gets plastered over.
My questions:
- How large should I make the duct? 40mm waste pipe, or 75mm guttering down pipe?
- What level should I pass it through the wall? I'll have 6 courses of brick between DPC and the top of the trench fill
- Where's best to bring it up? I guess it needs to be far enough into the wall that SWA can come out of the duct behind skirting board, which feels like it would need to be notched into the blocks under the DPC?
Thanks as always
I'm just setting out the footings for my new extension. 6 feet away is a shed that I envisage will need power and maybe a network cable in a couple of years.
I'd like to lay an underground duct now to make things easier and neater in future (outside will be rendered) , and then when I'm having the extension electrics first fixed I can ask the electrician to push through some SWA for future use before everything gets plastered over.
My questions:
- How large should I make the duct? 40mm waste pipe, or 75mm guttering down pipe?
- What level should I pass it through the wall? I'll have 6 courses of brick between DPC and the top of the trench fill
- Where's best to bring it up? I guess it needs to be far enough into the wall that SWA can come out of the duct behind skirting board, which feels like it would need to be notched into the blocks under the DPC?
Thanks as always