Hi, I am after some advice with regards to a raised/elevated patio project we hope to start shortly. Have not long moved in and our garden is reasonably long but on a gradual slope with lowest point at back door. We want to replace existing elevated decking 4m wide by 5m long (flush with ground at furthest point, and elevated by 3.5-4ft at other end). Our thoughts are to replace the decking with a concrete 'base'/platform, build in some steps, render blockwork and tile the top platform.
To do this we were thinking
-Build retaining wall with breeze-block inc footings
-Fill the big void with hardcore then whacker leaving 1ft
-Fill reaming 1ft with screed ready for tiles/slabs
-Render blockwork
-Finally, after approx 2weeks lay tiles on screed floor
Is there any other considerations or better approach for this project? Would something of this nature require planning permission (we are not overlooked!)
Thanks for any input/advice!
To do this we were thinking
-Build retaining wall with breeze-block inc footings
-Fill the big void with hardcore then whacker leaving 1ft
-Fill reaming 1ft with screed ready for tiles/slabs
-Render blockwork
-Finally, after approx 2weeks lay tiles on screed floor
Is there any other considerations or better approach for this project? Would something of this nature require planning permission (we are not overlooked!)
Thanks for any input/advice!