Hi all many thanks in advance for any help.
Basically fitting a new kitchen and wondering which is best to do next. All carcasses are made doors fitted etc....so im kind of ready for joining the units and getting them on the wall and leveling them. I still need to plumb in the washing machine and dish washer and sink. However , its a new extension so im also waiting on the final fix for electrician. So should i hold off till the electricain has been??.....any advice on this would be great or any general tips on fitting kitchens. TIA.
Basically fitting a new kitchen and wondering which is best to do next. All carcasses are made doors fitted etc....so im kind of ready for joining the units and getting them on the wall and leveling them. I still need to plumb in the washing machine and dish washer and sink. However , its a new extension so im also waiting on the final fix for electrician. So should i hold off till the electricain has been??.....any advice on this would be great or any general tips on fitting kitchens. TIA.