Hi
Could I ask anyone more experienced than myself their opinion on this situation.
Essentially I agreed a price with a builder including a fixed price for making a large family room and replacing the kitchen etc. This included a list of tasks and any other reasonable tasks to complete the above objective and make good.
The builder has nearly finished but now states he wants extra money. Some of this is not unreasonable (additional socket for the dishwasher, extra pop up socket on the work top as not specified originally) however a few things seem to be unfair and I would be interested in someone independents opinion:
1) Adjusting floor to make level following removal of the structural wall. The floors were not aligned (1cm out approx) but I am of the mind that this is not unforeseen and I struggle to see why an extra payment of £150 is required.
2) Plastering the other side of a blocked up door. The scope of works included the blocking up of an internal door as due to knocking the 2 rooms into 1 only 1 is required. It seems a little unfair that I have to pay extra £70 for both sides of the door to be made good.
Also some of his charges seem a little expensive (putting up tv bracket £70 and shelf £50). Seems a little high for screwing these to the wall.
Any thoughts would be very much appreciated.
Thanks
Could I ask anyone more experienced than myself their opinion on this situation.
Essentially I agreed a price with a builder including a fixed price for making a large family room and replacing the kitchen etc. This included a list of tasks and any other reasonable tasks to complete the above objective and make good.
The builder has nearly finished but now states he wants extra money. Some of this is not unreasonable (additional socket for the dishwasher, extra pop up socket on the work top as not specified originally) however a few things seem to be unfair and I would be interested in someone independents opinion:
1) Adjusting floor to make level following removal of the structural wall. The floors were not aligned (1cm out approx) but I am of the mind that this is not unforeseen and I struggle to see why an extra payment of £150 is required.
2) Plastering the other side of a blocked up door. The scope of works included the blocking up of an internal door as due to knocking the 2 rooms into 1 only 1 is required. It seems a little unfair that I have to pay extra £70 for both sides of the door to be made good.
Also some of his charges seem a little expensive (putting up tv bracket £70 and shelf £50). Seems a little high for screwing these to the wall.
Any thoughts would be very much appreciated.
Thanks