I am due to start the footings for the rear extension and have a question before i do.
The ground floor will be constructed from a traditional suspended timber floor using 200x50 joists requiring a 150mm clear void below the joists for ventilation (as per BC requirements). So a minimum of 350mm from top of joist to ground level.
The extension is sitting where the existing patio is. You step down from the house to the patio as shown in the photo below by approximately 400mm. The patio then slopes away from the house.
My question is can i juts cut the footings out of the patio and then dig down and use the existing patio as the concrete cover required to cap the ground or do i need to remove it all back to soil and start again.
I was planning on removing the lot but then thought why bother as i will be saving the muck away, digging and then reinstating a 50mm concrete covering afterwards?
What is the best way to deal with this?
The ground floor will be constructed from a traditional suspended timber floor using 200x50 joists requiring a 150mm clear void below the joists for ventilation (as per BC requirements). So a minimum of 350mm from top of joist to ground level.
The extension is sitting where the existing patio is. You step down from the house to the patio as shown in the photo below by approximately 400mm. The patio then slopes away from the house.
My question is can i juts cut the footings out of the patio and then dig down and use the existing patio as the concrete cover required to cap the ground or do i need to remove it all back to soil and start again.
I was planning on removing the lot but then thought why bother as i will be saving the muck away, digging and then reinstating a 50mm concrete covering afterwards?
What is the best way to deal with this?