- Joined
- 19 Apr 2022
- Messages
- 27
- Reaction score
- 0
- Country
I have 2 foul plastic pipes cutting through my foundations, which I have shuttered either side by 100mm to full depth of trench.
So effectively I now have a 300mm wide full depth cutting within the foundation run in 2 places.
Question:
Is this correct or should I be still pouring concrete underneath the pipes to say 100mm below pipework so that the concrete is continuous all be it a different depth
So effectively I now have a 300mm wide full depth cutting within the foundation run in 2 places.
Question:
Is this correct or should I be still pouring concrete underneath the pipes to say 100mm below pipework so that the concrete is continuous all be it a different depth