Hi everyone.
After some advice on where I go from here.
Builder gave us a total quote before starting an extension.
The quote inc the 1m footings.
It did specify in the quote that if BC wanted deeper footings then we would pay more which we would be told about if the time came. (no problem)
So before the foundations were poured, he had BC round and they "apparently" told him because we had conifers too close that we needed to go deeper to 1.5m and for 4m of conifers to be removed.
He rang us and told us this and the additional charge would be £2500.
We had to go with that as that's what BC wanted.
I was at home before they were poured and measured them at 1m deep.
We contacted BC to double check the information that the builder gave us and yes she confirmed we needed to take 4m of confier out but they were happy to go down 1m.
So this matches our original quote.
The additional work in this case was to dig out the confiers.
As the BC have confirmed they didn't need deeper foundations am I OK to argue the price of £2500 to take out the conifers?
Yes I understand 'additional work' was carried out but surely not paying for "imaginary deeper" foundations when I have pictures of the 1m trench.
Thanks
After some advice on where I go from here.
Builder gave us a total quote before starting an extension.
The quote inc the 1m footings.
It did specify in the quote that if BC wanted deeper footings then we would pay more which we would be told about if the time came. (no problem)
So before the foundations were poured, he had BC round and they "apparently" told him because we had conifers too close that we needed to go deeper to 1.5m and for 4m of conifers to be removed.
He rang us and told us this and the additional charge would be £2500.
We had to go with that as that's what BC wanted.
I was at home before they were poured and measured them at 1m deep.
We contacted BC to double check the information that the builder gave us and yes she confirmed we needed to take 4m of confier out but they were happy to go down 1m.
So this matches our original quote.
The additional work in this case was to dig out the confiers.
As the BC have confirmed they didn't need deeper foundations am I OK to argue the price of £2500 to take out the conifers?
Yes I understand 'additional work' was carried out but surely not paying for "imaginary deeper" foundations when I have pictures of the 1m trench.
Thanks