Garage Conversion - Planning Permission Needed?

Joined
30 Apr 2023
Messages
10
Reaction score
0
Country
United Kingdom
Hi,

We are looking to convert our garage into a home office. This will include replacing the asbestos roof with a new flat roof and adding a PVC window and door where the existing garage door is. I am trying to work out whether or not we need planning permission. A builder has said it falls under building regs.

The local authority said I need to complete a "Lawful Certificate – Proposed” form, but I have no plans drawn up. Can you submit such a form without plans?
 
Sponsored Links
A home office won't need building regulations.

For planning, it may well be permitted development. Check if the property has permitted development rights if so, crack on no need to fill any forms in or apply for anything.
 
Sponsored Links
It will be PD unless the property is in a Conservation Area or there was a condition on the planning permission for the original build which precludes the use for anything other than as a garage (i.e. the 'permitted development' rights have been removed) or the height of the roof is to be increased.

You don't have to submit a Certificate of Lawfulness application-this is entirely optional, and in my experience, not really worth it for householder developments.
 
It will be PD unless the property is in a Conservation Area or there was a condition on the planning permission for the original build which precludes the use for anything other than as a garage (i.e. the 'permitted development' rights have been removed) or the height of the roof is to be increased.

You don't have to submit a Certificate of Lawfulness application-this is entirely optional, and in my experience, not really worth it for householder developments.
Thanks for that. We applied for a certificate of lawfulness as the roof is being raised by around 4 inches. Found out today that the application is valid. Any idea how long these things take from there?
 
We applied for a certificate of lawfulness as the roof is being raised by around 4 inches
It's either PD or it's not. You didn't need to make an application if the slightly raised roof still falls within the PD parameters. Hopefully you won't open yourself up to some arbitrary planners opinion that starts a world of pain.
 
Thanks for that. We applied for a certificate of lawfulness as the roof is being raised by around 4 inches. Found out today that the application is valid. Any idea how long these things take from there?
It all depends on the workload of the officer. I would say 6 weeks as a guestimate. It is not a difficult application to deal with, and the Council won't need to write to neighbours or consult with any third parties. The reason they take a while is that, unlike applications for full planning permission, the government don't measure how long Councils take to determine them, so they end up going to the bottom of the pile.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top