Kitchen rebuild in 1920 semi - kitchen floor is solid, rest of ground floor is suspended with 3 foot void below. Current water main is lead and was shared with neighbour, actual route of water main unknown (but under solid floor). Gas main (15mm) routing is currently a nightmare - up,down, all around - total of 7 elbows. Siting of new boiler and cooker are still undecided, so I'm trying to cover all possibilities in terms of routing of pipes and cables
I've lifted the old quarry tiles in the kitchen prior to laying new slate floor, and it struck me that while floor is up I could cut a channel in the cement screed and embed a 4" plastic pipe from the site of the existing rising main to the void under the dining room to accommodate a new 22mm gas main and a 25mm plastic water main which could be installed at a later date with no disruption of the new floor.
This would provide much more direct routing of both water and gas to the correct side of the kitchen and also provide possible access for 'return leg' of new electric ring main.
Are there any reasons/regs that this is not a good idea?
I've lifted the old quarry tiles in the kitchen prior to laying new slate floor, and it struck me that while floor is up I could cut a channel in the cement screed and embed a 4" plastic pipe from the site of the existing rising main to the void under the dining room to accommodate a new 22mm gas main and a 25mm plastic water main which could be installed at a later date with no disruption of the new floor.
This would provide much more direct routing of both water and gas to the correct side of the kitchen and also provide possible access for 'return leg' of new electric ring main.
Are there any reasons/regs that this is not a good idea?