Hi
I'm planning to install a sanislim. When I first contacted the company a while back, they just mentioned that I should ensure any 'horizontal' discharge piping had a slight gradient. So, several years ago in preparation for it, I laid in a run of 22mm copper under the floor of another room.
I've now discovered the gradient should have been a min of 1:100 whereas the pre-installed piping is only at 1:150.
As I've faced difficulties finding a good connection between plastic and copper, I've already decided to pull the copper out through the exterior wall and replace it with 32mm solvent weld threaded back through the floor void.
In order to avoid lifting floor boards in the adjoining room, my question: is a drop of 1:150 in 32mm the equivalent of 1:100 in 22mm? I understand that this principal applies in larger diameter waste piping 1:150 for 150mm as compared with 1:80 for 110mm.
The pipe run will now be all in 32mm from the top of the unit turning almost immediately down into the floor void and run 'horizontally' some 11 metres to the main stack.
Many thanks
I'm planning to install a sanislim. When I first contacted the company a while back, they just mentioned that I should ensure any 'horizontal' discharge piping had a slight gradient. So, several years ago in preparation for it, I laid in a run of 22mm copper under the floor of another room.
I've now discovered the gradient should have been a min of 1:100 whereas the pre-installed piping is only at 1:150.
As I've faced difficulties finding a good connection between plastic and copper, I've already decided to pull the copper out through the exterior wall and replace it with 32mm solvent weld threaded back through the floor void.
In order to avoid lifting floor boards in the adjoining room, my question: is a drop of 1:150 in 32mm the equivalent of 1:100 in 22mm? I understand that this principal applies in larger diameter waste piping 1:150 for 150mm as compared with 1:80 for 110mm.
The pipe run will now be all in 32mm from the top of the unit turning almost immediately down into the floor void and run 'horizontally' some 11 metres to the main stack.
Many thanks