Hello,

I have dug my footings to the sizes that I need to build a conservatory.
I need to fill in 2.7 yrds3
With a mix of 6-1 ballast to cement how much of each will I need to fill my footings?

thanks for any help
 
Sponsored Links
2.7 cubic yards is a little over 2m3, so you will need 4 tonnes of ballast and 26 x 25kg bags of cement.
 
Thankyou,
Will I need to put hard core (type1) and sharp sand at the bottom for a good bed to pour the concrete on to?
 
Sponsored Links
I'm building on clay. Does that make a difference as I was advised to lay sand and h/core first? My trench is 450m/m wide *600m/m deep.
 
I'm building on clay. Does that make a difference as I was advised to lay sand and h/core first? My trench is 450m/m wide *600m/m deep.

The person that gave you this advice has not the first clue.

If there happens to be a bit of water in the trench then mix the first lot semi dry then fill with regular concrete.

If there happens to be a lot of water in the trench then bail it out then do the above.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top