Agreement: 9 day job, ready by Sat 29th Sept…it's a 3bed flat. Labour quote £5.5k.
(i) tidy up as discussed per room (bedroom flooring, walls, skirting tidy up, locks, fire alarms, tv outlet points etc). (ii) 2 separate WCs with sinks (refurbing one and the other is a cupboard being converted into a toilet) (iii) fix up bathroom. New suite, decent extraction etc. (iv) keep kitchen units, replace worktops. Cover boiler. New dual fuel cooker not far off what is there already but with decent extraction...
16th Sept I sent a £2.5 deposit. was meant to start 20th Sept:
1. started job 1week later than agreed
2. prep could have started as soon as he received £ – I know for a fact everyone was available to do work as they have told me
3. underestimated materials costs – advised roughly £2k, infact it’s over double that now
4. measurements incorrect – too few tiles, wrong toilet which I consulted him/his team about before buying. Some of the tiling is no good, sitting in the "cowboy" category. eg tiling in the wc where there has been no space left for beading and so the standard looks low.
5. not giving due attention when inspecting/offering quote, nor before jobs are started = more delays as requirements not identified, project manager arrives mid-late afternoon finding we don’t have appropriate materials to complete a job + too late in the day to source them, his men have been doing jobs unsupervised+plenty of mistakes have been made as a result
6. once original deadline not reached, advised bathroom, kitchen and wc by Thursday 4th October. Now saying he will complete this by Mon 8th Oct.
7. Not fulfilled a single agreement or schedule. Every room is only part done.
8. They've been working 1/2 days for the most part. Only 3 days were there have been full days’ worth of work carried out. My job does not seem to have any priority. Jobs that can be completed in 1 day have taken 3 or more days.
9. no project management: client living in the site, should have prepared the workmen + the job in such a way that I could still live comfortably. Promised me working bath but in fact has only carried out quick fix measures leaving me with a leaking bath.
10. I coughed up all sorts of crap from living in the site for longer than advised I would be
11. wants to agree extra payment for jobs not in the original quote, but he hasn't even honoured the original schedule + any "add ons" are because he didn't inspect the property thoroughly at any point whatsoever.
Cannot say he has even earnt the deposit I have paid him. I want the job to end and I want £1000 back, or I am willing to take this to court.
was referred to me by a Landlord, so I had good faith that he was capable of doing a good job to a high standard.
.....right now I'm thinking put all his tools outside tomorrow AM, not let him back in + demand £1000 back from my deposit, give the job to someone else. it's affecting my business and my health. advice please?
(i) tidy up as discussed per room (bedroom flooring, walls, skirting tidy up, locks, fire alarms, tv outlet points etc). (ii) 2 separate WCs with sinks (refurbing one and the other is a cupboard being converted into a toilet) (iii) fix up bathroom. New suite, decent extraction etc. (iv) keep kitchen units, replace worktops. Cover boiler. New dual fuel cooker not far off what is there already but with decent extraction...
16th Sept I sent a £2.5 deposit. was meant to start 20th Sept:
1. started job 1week later than agreed
2. prep could have started as soon as he received £ – I know for a fact everyone was available to do work as they have told me
3. underestimated materials costs – advised roughly £2k, infact it’s over double that now
4. measurements incorrect – too few tiles, wrong toilet which I consulted him/his team about before buying. Some of the tiling is no good, sitting in the "cowboy" category. eg tiling in the wc where there has been no space left for beading and so the standard looks low.
5. not giving due attention when inspecting/offering quote, nor before jobs are started = more delays as requirements not identified, project manager arrives mid-late afternoon finding we don’t have appropriate materials to complete a job + too late in the day to source them, his men have been doing jobs unsupervised+plenty of mistakes have been made as a result
6. once original deadline not reached, advised bathroom, kitchen and wc by Thursday 4th October. Now saying he will complete this by Mon 8th Oct.
7. Not fulfilled a single agreement or schedule. Every room is only part done.
8. They've been working 1/2 days for the most part. Only 3 days were there have been full days’ worth of work carried out. My job does not seem to have any priority. Jobs that can be completed in 1 day have taken 3 or more days.
9. no project management: client living in the site, should have prepared the workmen + the job in such a way that I could still live comfortably. Promised me working bath but in fact has only carried out quick fix measures leaving me with a leaking bath.
10. I coughed up all sorts of crap from living in the site for longer than advised I would be
11. wants to agree extra payment for jobs not in the original quote, but he hasn't even honoured the original schedule + any "add ons" are because he didn't inspect the property thoroughly at any point whatsoever.
Cannot say he has even earnt the deposit I have paid him. I want the job to end and I want £1000 back, or I am willing to take this to court.
was referred to me by a Landlord, so I had good faith that he was capable of doing a good job to a high standard.
.....right now I'm thinking put all his tools outside tomorrow AM, not let him back in + demand £1000 back from my deposit, give the job to someone else. it's affecting my business and my health. advice please?