Hi,
We are in the process of installing a large array of blade computer servers and we are experiencing a few problems whilst connecting them to our outlets, any help would be gratefully received.
In short, each rack of servers has four 32A CEE connectors of which one supplies the internal fans and the rest supply a row of servers each.
As soon as we plug the fans connector into the socket the RCBO trips, and without the fans connected the servers won't start up.
We have checked all the connections etc and can't find a problem. The only reason we can see is from a label on the unit which says the following: High Leakage Current Earth Connection needed before connecting Supply.
What does this mean, and how do we go about connecting this up?
Kind regards,
Matthew
We are in the process of installing a large array of blade computer servers and we are experiencing a few problems whilst connecting them to our outlets, any help would be gratefully received.
In short, each rack of servers has four 32A CEE connectors of which one supplies the internal fans and the rest supply a row of servers each.
As soon as we plug the fans connector into the socket the RCBO trips, and without the fans connected the servers won't start up.
We have checked all the connections etc and can't find a problem. The only reason we can see is from a label on the unit which says the following: High Leakage Current Earth Connection needed before connecting Supply.
What does this mean, and how do we go about connecting this up?