My neighbour signed the party wall act document with regards to my loft conversion about 18 months ago. Is it still valid or would I need to have another one signed?
How long in advance do I have to serve the notice
At least two months before the planned starting date for work to the party wall.
The Adjoining Owner may agree to allow works to start earlier but is not obliged to
even when agreement on the works is reached. The notice is only valid for a year,
so do not serve it too long before you wish to start