Hi
How can I maintain the integrity of the 1200 gauge d.p.m for a new floor - when the d.p.m is going to be
pierced horizontally by R10 rebar (6 metres wide extension - rebar every 200mm at centres)?
The rebar itself is a "Z" shape - the bottom section of the "Z" will be connected to a reinforced raft
filled with C35 lower down in the excavation.
The top of the "Z" locks the new floor to the raft.
The concrete slab will be 125mm.
The length of the rebar for the new floor (top of "Z") is 300mm
Looking on Google I've seen service pipes etc coming through d.p.m but I can't see how they seal
the cut.
Just as a side issue if this has any bearing - the structural engineer has changed what the original
architect had specified for the new floor, because I explained to him that the rebar will not line up
with the concrete but the insulation. So he said to put the insulation on top of the slab.
This is the original spec;
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
The new floor is to be 100mm blinded hardcore bed, 1200 gauge
polythene d.p.m. followed by 70mm Kingspan floor insulation, 500 gauge
polythene vapour barrier, 125mm concrete slab and finished with
50mm C&S (1:4) screed towelled smooth.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
This is the revised spec;
In these cases the insulation goes on top of the slab. You adjust the concrete slab to let your
screed finish over the insulation to match existing floor levels. Your screed needs to be min of 65mm
when cast over insulation. This method will also give you a warmer floor.
Then there will be no conflict with reinforcement.
Any help/advice appreciated.
Many thanks.
Stephen
How can I maintain the integrity of the 1200 gauge d.p.m for a new floor - when the d.p.m is going to be
pierced horizontally by R10 rebar (6 metres wide extension - rebar every 200mm at centres)?
The rebar itself is a "Z" shape - the bottom section of the "Z" will be connected to a reinforced raft
filled with C35 lower down in the excavation.
The top of the "Z" locks the new floor to the raft.
The concrete slab will be 125mm.
The length of the rebar for the new floor (top of "Z") is 300mm
Looking on Google I've seen service pipes etc coming through d.p.m but I can't see how they seal
the cut.
Just as a side issue if this has any bearing - the structural engineer has changed what the original
architect had specified for the new floor, because I explained to him that the rebar will not line up
with the concrete but the insulation. So he said to put the insulation on top of the slab.
This is the original spec;
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
The new floor is to be 100mm blinded hardcore bed, 1200 gauge
polythene d.p.m. followed by 70mm Kingspan floor insulation, 500 gauge
polythene vapour barrier, 125mm concrete slab and finished with
50mm C&S (1:4) screed towelled smooth.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
This is the revised spec;
In these cases the insulation goes on top of the slab. You adjust the concrete slab to let your
screed finish over the insulation to match existing floor levels. Your screed needs to be min of 65mm
when cast over insulation. This method will also give you a warmer floor.
Then there will be no conflict with reinforcement.
Any help/advice appreciated.
Many thanks.
Stephen