Insulation under or above concrete slab

Joined
2 Sep 2015
Messages
336
Reaction score
7
Country
United Kingdom
I have a floor (above a basement) which is constructed using Block and Beams. Under the B&B will be 25mm of insulation, Rockwool RWA45. Above will be 25mm Celotex rigid board, membrane sheet, UFH pipes and then 50mm of liquid screed.

To the side of the area in question is backfill (around the basement and original property). Would it be best practice to have 100mm of Celotex PIR under the concrete slab, or on top?

So:

50mm Liquid Screed
UFH Pipes
Concrete Slab
Membrane
100mm of Insulation
DPM
Sand
Hardcore
Earth


or:

50mm Liquid Screed
UFH Pipes
Membrane
100mm of Insulation
Concrete Slab
DPM
Sand
Hardcore
Earth
 
Sponsored Links
I have a floor (above a basement) which is constructed using Block and Beams. Under the B&B will be 25mm of insulation, Rockwool RWA45. Above will be 25mm Celotex rigid board, membrane sheet, UFH pipes and then 50mm of liquid screed.

To the side of the area in question is backfill (around the basement and original property). Would it be best practice to have 100mm of Celotex PIR under the concrete slab, or on top?

So:

50mm Liquid Screed
UFH Pipes
Concrete Slab
Membrane
100mm of Insulation
DPM
Sand
Hardcore
Earth


or:

50mm Liquid Screed
UFH Pipes
Membrane
100mm of Insulation
Concrete Slab
DPM
Sand
Hardcore
Earth
Second option for UFH except the membrane goes down before the insulation.
 

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Sponsored Links
Back
Top