We're building a kitchen extension where a steel is going in to open up the old external wall to the extension.
Because winter is coming, is it ok to put the door and window in first? Initially I was thinking of having the steel delivered and in waiting in the extension to be fitted at a later date before the window and door goes in but, as a wall is coming out there should be enough room to get the beam in after the wall is down?
Because winter is coming, is it ok to put the door and window in first? Initially I was thinking of having the steel delivered and in waiting in the extension to be fitted at a later date before the window and door goes in but, as a wall is coming out there should be enough room to get the beam in after the wall is down?