Hi all,
In the process of finalising electrical design for a new house. Unfortunately the meter box is in a position which requires the meter tails to be run internally for about 5m - this is the total distance from the meter to the CU. The meter box has an 80A fused switch fitted - DNO said they don't have problem with this. This will allow more than the normal maximum of 3m tails to be run to the CU from this switch.
The problem is with the internal run of meter tails where they come through from the meter box and fused switch. If I understand the 17th edition correctly then I have the following options:
1. Bury the meter tails in excess of 50mm into the internal blockwork and run them to the CU. I understand that they must also be run within the safe zones.
2. Mechanically protect the tails with steel conduit and run to the CU. This conduit would also require earthing. I understand that galvanised capping is NOT sufficient as it doesn't offer mechanical protection.
Issue with option 1 is obviously burying the cable and also creating a safe zone where the cable runs up from the point of entry. I had thought of putting a back box into the internal wall with a blanking plate thereby providing a visual indication for the vertical run towards the ceiling. Option 1 also entails a large degree of channelling which is time consuming.
Option 2 has the issue of still having to channel the conduit partly into the wall so as it won't be seen and earthing it. Would 25mm conduit be sufficient to get both live and neutral tails into easily?
Anyone think of any other options or does anyone think the interpretation of the regs is wrong? Spoken with several electricians and have had several different answers!
Thanks for the help.
In the process of finalising electrical design for a new house. Unfortunately the meter box is in a position which requires the meter tails to be run internally for about 5m - this is the total distance from the meter to the CU. The meter box has an 80A fused switch fitted - DNO said they don't have problem with this. This will allow more than the normal maximum of 3m tails to be run to the CU from this switch.
The problem is with the internal run of meter tails where they come through from the meter box and fused switch. If I understand the 17th edition correctly then I have the following options:
1. Bury the meter tails in excess of 50mm into the internal blockwork and run them to the CU. I understand that they must also be run within the safe zones.
2. Mechanically protect the tails with steel conduit and run to the CU. This conduit would also require earthing. I understand that galvanised capping is NOT sufficient as it doesn't offer mechanical protection.
Issue with option 1 is obviously burying the cable and also creating a safe zone where the cable runs up from the point of entry. I had thought of putting a back box into the internal wall with a blanking plate thereby providing a visual indication for the vertical run towards the ceiling. Option 1 also entails a large degree of channelling which is time consuming.
Option 2 has the issue of still having to channel the conduit partly into the wall so as it won't be seen and earthing it. Would 25mm conduit be sufficient to get both live and neutral tails into easily?
Anyone think of any other options or does anyone think the interpretation of the regs is wrong? Spoken with several electricians and have had several different answers!
Thanks for the help.