Hi all,
First post! Done a search but can't find the answer, so any advice appreciated.
I have a cottage with a dodgy extension which is due to be demolished and rebuilt (the extension only). The current Electric meter and CU is on a wall that's due to be demolished, and ideally we'd like the CU replaced in roughly the same position when the extension is rebuilt.
The whole house will be re-wired at some point and it's an overhead supply feed.
I'm thinking of getting an external box for the meter and an isolation switch fitted - which Western Power can do. Is it acceptable to fit a second 'temporary' external box (same spec as WP supplied box) adjacent to it with a temporary CU in and a couple of sockets for site power installed? I can then rewire house with proper CU and connect up tails from outside meter to new CU when done and loose the second external box?
Is it good practice to run meter tails outside from the meter box to the new entry point into the building to meet the new CU? Is SWA or conduit needed in this case?
Will Western Power connect to the temp CU only if the CU is all installed, and signed off or will they leave unconnected on the isolator switch?
I will be using a registered sparky - just want to have some advice first to gauge the job!
Thanks.
First post! Done a search but can't find the answer, so any advice appreciated.
I have a cottage with a dodgy extension which is due to be demolished and rebuilt (the extension only). The current Electric meter and CU is on a wall that's due to be demolished, and ideally we'd like the CU replaced in roughly the same position when the extension is rebuilt.
The whole house will be re-wired at some point and it's an overhead supply feed.
I'm thinking of getting an external box for the meter and an isolation switch fitted - which Western Power can do. Is it acceptable to fit a second 'temporary' external box (same spec as WP supplied box) adjacent to it with a temporary CU in and a couple of sockets for site power installed? I can then rewire house with proper CU and connect up tails from outside meter to new CU when done and loose the second external box?
Is it good practice to run meter tails outside from the meter box to the new entry point into the building to meet the new CU? Is SWA or conduit needed in this case?
Will Western Power connect to the temp CU only if the CU is all installed, and signed off or will they leave unconnected on the isolator switch?
I will be using a registered sparky - just want to have some advice first to gauge the job!
Thanks.