I have planning permission for an extension, two storey behind garage and single storey above. The garage is attached to the side of the house and we are filling in the bit behind it.
The garage is just under 3m wide, the two storey section is approx 4m long and the garage is approx 6m long. We want a cut roof to maximise the storage space.
I have spend significant amounts of time calculating out quantities of materials and getting quotes from local Builders Merchants.
After having 6 different Builders visit to quote (Over a 3 month period because they never came back to me with prices) I have finally started to get some prices in. Although I only really want a price for sewage, shell inc roof and knock through's, one builder mistakenly quoted for all of it at £68,000!
Here's the breakdown I have estimated, assume each days labour will be for mimimum 1 tradesman + 1 labourer:-
Sewage & Foundations - 6m run and T into existing pipes (Up to 4ft down) and install inspection chamber. Dig out foundations with mini digger, dispose of soil. Pour foundations, install insulation etc.
Materials - £974.57 (Inc tips for soil, readymix concrete, DPM, hardcore, insulation & vapour barrier)
Labour - 6 days (with mini digger)
Walls - Build insulated cavity walls including removing some of existing garage wall, roof from garage etc. up to wall plate.
Materials - £3,768.88
Labour - 10 days
New windows and doors - For extension only
Materials - £1,527.66 (UPVC, mahogany out/white in to match existing)
Labour - 4 days
Roof - Cut std pitched roof with gable on end, 1m dormer on front elevation.
Materials - £1,276.75 (Existing garage tiles reused, inc 2 skylights)
Labour - 5 days
Knock throughs - Remove adjoining wall into kitchen and install RSJ(3m long), remove wall from kitchen to dining room and install RSJ (3m long), remove wall on landing and install RSJ(2.5m long)
Materials - £500
Labour - 3 days
Internal work - insulation, plasterboard, floorboards etc.
Materials - £2,063.57
Labour - £1,700 (Plasterer only, as I will do rest)
Electrical & Plumbing, fixtures - Inc kitchen, shower room.
Materials - £6,785.30
Labour - 1 day (Sparky to check and test my work)
New boiler
Materials & Labour - £2,000
Paint, floor coverings etc
Materials - £1,284.00
There are a few minor items I have missed of but the total cost estimated is:-
Materials - £23,000 (Inc boiler install)
Labour - 29 days
Plasterer - £1,700
With a builder at £200 a day inc labourer this would be £23,000 + £5,800 + £1,700 + VAT = £ 35,837.50
Does this all sound reasonable or am I being shortsighted?
Any comments welcomed as I am hoping to project manage and do as much as I can myself (Even though it will take a LONG time!)
I have very detailed spreadsheets if anybody wanted to take a further look.
The garage is just under 3m wide, the two storey section is approx 4m long and the garage is approx 6m long. We want a cut roof to maximise the storage space.
I have spend significant amounts of time calculating out quantities of materials and getting quotes from local Builders Merchants.
After having 6 different Builders visit to quote (Over a 3 month period because they never came back to me with prices) I have finally started to get some prices in. Although I only really want a price for sewage, shell inc roof and knock through's, one builder mistakenly quoted for all of it at £68,000!
Here's the breakdown I have estimated, assume each days labour will be for mimimum 1 tradesman + 1 labourer:-
Sewage & Foundations - 6m run and T into existing pipes (Up to 4ft down) and install inspection chamber. Dig out foundations with mini digger, dispose of soil. Pour foundations, install insulation etc.
Materials - £974.57 (Inc tips for soil, readymix concrete, DPM, hardcore, insulation & vapour barrier)
Labour - 6 days (with mini digger)
Walls - Build insulated cavity walls including removing some of existing garage wall, roof from garage etc. up to wall plate.
Materials - £3,768.88
Labour - 10 days
New windows and doors - For extension only
Materials - £1,527.66 (UPVC, mahogany out/white in to match existing)
Labour - 4 days
Roof - Cut std pitched roof with gable on end, 1m dormer on front elevation.
Materials - £1,276.75 (Existing garage tiles reused, inc 2 skylights)
Labour - 5 days
Knock throughs - Remove adjoining wall into kitchen and install RSJ(3m long), remove wall from kitchen to dining room and install RSJ (3m long), remove wall on landing and install RSJ(2.5m long)
Materials - £500
Labour - 3 days
Internal work - insulation, plasterboard, floorboards etc.
Materials - £2,063.57
Labour - £1,700 (Plasterer only, as I will do rest)
Electrical & Plumbing, fixtures - Inc kitchen, shower room.
Materials - £6,785.30
Labour - 1 day (Sparky to check and test my work)
New boiler
Materials & Labour - £2,000
Paint, floor coverings etc
Materials - £1,284.00
There are a few minor items I have missed of but the total cost estimated is:-
Materials - £23,000 (Inc boiler install)
Labour - 29 days
Plasterer - £1,700
With a builder at £200 a day inc labourer this would be £23,000 + £5,800 + £1,700 + VAT = £ 35,837.50
Does this all sound reasonable or am I being shortsighted?
Any comments welcomed as I am hoping to project manage and do as much as I can myself (Even though it will take a LONG time!)
I have very detailed spreadsheets if anybody wanted to take a further look.