Because I am known by both parties, I have been asked to help find an amicable solution, without resorting to going to court. However, I could do with some pointers. The situation is:
A neighbour of mine is currently having a two storey extension built on the back of his house, the original quotation, plus an agreed extra to increase the extension by 600mm so that it missed some drains comes to £30,000
As the work progressed, various extra items were added; some due to the request of the homeowner, others due to unexpected extra works. Most of the other requested extras are relatively small, such as asking for a stud wall to an en-suite to be erected in a different position to that shown on the plans to increase the size of the room slightly, the same for a utility room downstairs, and to cut a hole in the plasterboard ceiling for a cooker chimney.
There were some unexpected extras. When the original upstairs windows were removed, because there were no lintels above, the gable end dropped and had to be demolished. Also the ground floor wall was deemed to be not in a sound condition to support the new steels and was rebuilt.
Also, there were some delays due to about one week of bad weather and the failure of deliveries, primarily the roof tiles which delayed the work for a further two days. The builder has now presented a bill for an extra £10,000 for the unexpected extras, which includes additional skips to get rid of the demolished gable end and wall.
In addition to this, the new floor slopes upwards from the new external wall to meet with the original kitchen floor, so that there is about a 50mm difference in height over a 3 metre distance. When someone came to fit the wooden floor, he said he couldn’t install it because of this. The builder explained that this was because the new floor was levelled to the existing kitchen floor at one end, but the other end of the exisiting floor was different. He says he can only rectify the situation by digging up the entire floor and relaying it and that it will incur a further cost of about £900.
Initially the work was estimated to take 8 weeks with completion mid June, it is now 14 weeks since the start, and there is still some work to be finished guttering / flashing / plaster boarding a bedroom ceiling. The builder says that the time is because of the extras including the 600mm length increase, bad weather and being let down by suppliers.
Because of this, the homeowner believes that the builder is not competent to complete the work, and should leave site. He has paid him £30,000 but feels that he should not pay anymore for the extras, and that builder should reimburse the homeowner what it costs to get the work finished off to a satisfactory standard.
The builder says that the homeowner will be charged interest if he doesn’t pay the extra £10,000 and that if the homeowner gets someone else in to do the work, the homeowner he will be in breach of contract. For example:
Is it appropriate to ask for extra for the unexpected work mentioned above?
Is the householder right to ask the builder to leave site?
Is the householder in breach of contract if he asks someone else to finish the work?
A neighbour of mine is currently having a two storey extension built on the back of his house, the original quotation, plus an agreed extra to increase the extension by 600mm so that it missed some drains comes to £30,000
As the work progressed, various extra items were added; some due to the request of the homeowner, others due to unexpected extra works. Most of the other requested extras are relatively small, such as asking for a stud wall to an en-suite to be erected in a different position to that shown on the plans to increase the size of the room slightly, the same for a utility room downstairs, and to cut a hole in the plasterboard ceiling for a cooker chimney.
There were some unexpected extras. When the original upstairs windows were removed, because there were no lintels above, the gable end dropped and had to be demolished. Also the ground floor wall was deemed to be not in a sound condition to support the new steels and was rebuilt.
Also, there were some delays due to about one week of bad weather and the failure of deliveries, primarily the roof tiles which delayed the work for a further two days. The builder has now presented a bill for an extra £10,000 for the unexpected extras, which includes additional skips to get rid of the demolished gable end and wall.
In addition to this, the new floor slopes upwards from the new external wall to meet with the original kitchen floor, so that there is about a 50mm difference in height over a 3 metre distance. When someone came to fit the wooden floor, he said he couldn’t install it because of this. The builder explained that this was because the new floor was levelled to the existing kitchen floor at one end, but the other end of the exisiting floor was different. He says he can only rectify the situation by digging up the entire floor and relaying it and that it will incur a further cost of about £900.
Initially the work was estimated to take 8 weeks with completion mid June, it is now 14 weeks since the start, and there is still some work to be finished guttering / flashing / plaster boarding a bedroom ceiling. The builder says that the time is because of the extras including the 600mm length increase, bad weather and being let down by suppliers.
Because of this, the homeowner believes that the builder is not competent to complete the work, and should leave site. He has paid him £30,000 but feels that he should not pay anymore for the extras, and that builder should reimburse the homeowner what it costs to get the work finished off to a satisfactory standard.
The builder says that the homeowner will be charged interest if he doesn’t pay the extra £10,000 and that if the homeowner gets someone else in to do the work, the homeowner he will be in breach of contract. For example:
Is it appropriate to ask for extra for the unexpected work mentioned above?
Is the householder right to ask the builder to leave site?
Is the householder in breach of contract if he asks someone else to finish the work?