Hi,
I am due to start a new build semi-detached house in May which will be attached to my current detached house. I am just in the progress of agreeing a builder and have 2 questions:
• The builders quote has no mention of including costs hooking up to services but it says local authority fees are not included. Do I assume I need to sort out the services payments side of things? I guess I will ask but just wondering what is normal.
• Is there any point going about looking at services now if the build isn’t until May, not sure of the services timescales or what they could even do before it starts?
Thanks
I am due to start a new build semi-detached house in May which will be attached to my current detached house. I am just in the progress of agreeing a builder and have 2 questions:
• The builders quote has no mention of including costs hooking up to services but it says local authority fees are not included. Do I assume I need to sort out the services payments side of things? I guess I will ask but just wondering what is normal.
• Is there any point going about looking at services now if the build isn’t until May, not sure of the services timescales or what they could even do before it starts?
Thanks