I'm in a bit of a bind. I'm currently in Temporary Local Authority owned housing [In Scotland], But been told That I could easily be here for upto 2years. Hence why I'm even bothering to investigate this matter further.
I am a time served Technician/Electrician. I only lack the official Qualifications, But my work has always been Signed off & Tested post Install, [With photos & Write-ups provided the whole way through] By a Certified sparky that shadowed me on a couple of installs back in the early days, to get a feel of MY Competency.
I try to keep up-to-date, and Currently own 16th, 17th And now 18th {+A2:2022} Regs, Plus the various Additional Guides (on-site, Guide to building Regs, and Guide to temporary Installations, etc), And my installs are Always, over and above what is expected. For which I refuse to do any less (Autism thing).
The property that I've been placed in, is presumably Post 2nd war (Has Cavity walls). I also discovered that the previous workies had kindly dumped all their electrical waste [and all other building waste] under the floor boards. {I did find the Original MK & Crabtree Bakelite toggle switches under there}.
The CU is setup split load (Non-RCD & RCD). {Lighting, Boiler, Smoke detectors and Cooker on the NON-RCD Side}
The kitchen is the only Room that appears to have had a rewire, since the Colours changed in 2004/6 But the rewire ONLY extends upto the 1st & last points of It's ring.
This is the same for the cooker circuit. Except that unlike the original lighting circuits, There is is NO steel conduit at any point in the run. . .
Based on the evidence found under the floor. The current setup is it's 2nd or 3rd rewire. But given that everything else [Bar the carbon monoxide detector in the kitchen] is still wired in old colours. Who knows Just how old it all actually is since the Lead, and clothed cables were removed (only small remnants of them were each found).
So, the Issue. The cocker circuit has had a semi-fresh rewire at some point in its life. Now given that its wired in 'new colours' Then it MUST come under either the 17th or the 18th Regs. Yet it's install does Not meet one or more of the requirements as stated in either Revision. . . ! There is NO Steel/Earth conduit, There is NO Earthed Metallic Sheath, and there is NO RCD or RCBO Protection for it's circuit.
Atop of this, there is a Remote Double socket also attached to the circuit, directly beside the cooker outlet , This of which is easily accessed by an 'Ordinary person'.
Via 'TLC' weblinks (as I don't have a camera) This is how the setup has been wired:
Wylex 32A MCB (From the Isolator) = https://www.tlc-direct.co.uk/Products/WYNHXB32.html {Seemingly its all in 6mm T+E}
\/
Cooker Switch = https://www.tlc-direct.co.uk/Products/CB4016slash3.html
\/
DBL + SGL Flush metal back box = https://www.tlc-direct.co.uk/Products/AP540.html
\/
DP DBL Socket = https://www.tlc-direct.co.uk/Products/CB4306D.html
\/
Cooker Outlet plate = https://www.tlc-direct.co.uk/Products/CB4506.html
Now Logic, (IF your were ever going to wire such a setup) would tell you to wire up the outlet with the highest Expected load first. But no! the cooker spur Piggybacks of the DBL socket, which as a result, The socket has 2x 6mm cores stuffed into the back of each terminal!
I have raised this already with the councils Repairs department, and had one of their sparkies out. And they argue that the setup is perfectly fine, and has passed all of it's Inspections. Including "having been tested on a special machine, that tells them that the circuits are up to code". . yeah. well that machine is clearly faulty given all the issues that I've discovered so far . . .!
They argue that this DBD SKT is required for a Gas hob, for the ignition circuit. Yet its a freestanding cooker. Without gas even run to it in the first place. For which If their argument was Legit. Then I would expect to see a fused Spur beside the Cooker spur for Such a very purpose. NOT a DBL SKT!
Both my own experience, and the Regs tell me That they're talking garbage. And are trying to get out of having to rectify this issue [And likely all the other properties that they've done the same way]. - For starters. I cannot find Anywhere [in the domestic setting] the mention of a remote 13A socket on a cooker circuit. Let alone a Double socket. Everything refers to a Single socket as part of a cooker switch unit, and to factor in 5A for it, when calculating the load diversity.
Secondly, The T+E cable Is Not buried more than 50mm, and as I mentioned at the start. There's no Earthed conduit or Earthed Metallic Sheath, at any point in its run, Nor even an RCD or RCBO protecting it.
And while Yes. I do know how to keep myself safe, or I could rewire it myself. - But at the end of the Day a) the next resident is very unlikely to have the same knowledge that I have, And b) I'm not supposed to be altering any of it in the first place as its still a local authority property and I'm Not a permanent resident of.
As it stands. They Refuse to rectify it, and I Refuse to use the cooker (That is also awaiting replacement too, as previous residents Both Human & Rodent. Neglected to care for the appliance. . .)
_ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ __ _ _ _
My hope, is that someone out there has come across this before, and can direct me to Any Requirements, Rules, etc so that I can force their hand into doing this remedial work. . .
Somewhere in my mind, I seem to recall that Certain Properties (Hospitals, Care homes, rentals, etc)are required to keep Electrical [and Gas] systems upto date with the current regulations. But I cannot find this information at this time :/
Thanks Gals & Guys
I am a time served Technician/Electrician. I only lack the official Qualifications, But my work has always been Signed off & Tested post Install, [With photos & Write-ups provided the whole way through] By a Certified sparky that shadowed me on a couple of installs back in the early days, to get a feel of MY Competency.
I try to keep up-to-date, and Currently own 16th, 17th And now 18th {+A2:2022} Regs, Plus the various Additional Guides (on-site, Guide to building Regs, and Guide to temporary Installations, etc), And my installs are Always, over and above what is expected. For which I refuse to do any less (Autism thing).
The property that I've been placed in, is presumably Post 2nd war (Has Cavity walls). I also discovered that the previous workies had kindly dumped all their electrical waste [and all other building waste] under the floor boards. {I did find the Original MK & Crabtree Bakelite toggle switches under there}.
The CU is setup split load (Non-RCD & RCD). {Lighting, Boiler, Smoke detectors and Cooker on the NON-RCD Side}
The kitchen is the only Room that appears to have had a rewire, since the Colours changed in 2004/6 But the rewire ONLY extends upto the 1st & last points of It's ring.
This is the same for the cooker circuit. Except that unlike the original lighting circuits, There is is NO steel conduit at any point in the run. . .
Based on the evidence found under the floor. The current setup is it's 2nd or 3rd rewire. But given that everything else [Bar the carbon monoxide detector in the kitchen] is still wired in old colours. Who knows Just how old it all actually is since the Lead, and clothed cables were removed (only small remnants of them were each found).
So, the Issue. The cocker circuit has had a semi-fresh rewire at some point in its life. Now given that its wired in 'new colours' Then it MUST come under either the 17th or the 18th Regs. Yet it's install does Not meet one or more of the requirements as stated in either Revision. . . ! There is NO Steel/Earth conduit, There is NO Earthed Metallic Sheath, and there is NO RCD or RCBO Protection for it's circuit.
Atop of this, there is a Remote Double socket also attached to the circuit, directly beside the cooker outlet , This of which is easily accessed by an 'Ordinary person'.
Via 'TLC' weblinks (as I don't have a camera) This is how the setup has been wired:
Wylex 32A MCB (From the Isolator) = https://www.tlc-direct.co.uk/Products/WYNHXB32.html {Seemingly its all in 6mm T+E}
\/
Cooker Switch = https://www.tlc-direct.co.uk/Products/CB4016slash3.html
\/
DBL + SGL Flush metal back box = https://www.tlc-direct.co.uk/Products/AP540.html
\/
DP DBL Socket = https://www.tlc-direct.co.uk/Products/CB4306D.html
\/
Cooker Outlet plate = https://www.tlc-direct.co.uk/Products/CB4506.html
Now Logic, (IF your were ever going to wire such a setup) would tell you to wire up the outlet with the highest Expected load first. But no! the cooker spur Piggybacks of the DBL socket, which as a result, The socket has 2x 6mm cores stuffed into the back of each terminal!
I have raised this already with the councils Repairs department, and had one of their sparkies out. And they argue that the setup is perfectly fine, and has passed all of it's Inspections. Including "having been tested on a special machine, that tells them that the circuits are up to code". . yeah. well that machine is clearly faulty given all the issues that I've discovered so far . . .!
They argue that this DBD SKT is required for a Gas hob, for the ignition circuit. Yet its a freestanding cooker. Without gas even run to it in the first place. For which If their argument was Legit. Then I would expect to see a fused Spur beside the Cooker spur for Such a very purpose. NOT a DBL SKT!
Both my own experience, and the Regs tell me That they're talking garbage. And are trying to get out of having to rectify this issue [And likely all the other properties that they've done the same way]. - For starters. I cannot find Anywhere [in the domestic setting] the mention of a remote 13A socket on a cooker circuit. Let alone a Double socket. Everything refers to a Single socket as part of a cooker switch unit, and to factor in 5A for it, when calculating the load diversity.
Secondly, The T+E cable Is Not buried more than 50mm, and as I mentioned at the start. There's no Earthed conduit or Earthed Metallic Sheath, at any point in its run, Nor even an RCD or RCBO protecting it.
And while Yes. I do know how to keep myself safe, or I could rewire it myself. - But at the end of the Day a) the next resident is very unlikely to have the same knowledge that I have, And b) I'm not supposed to be altering any of it in the first place as its still a local authority property and I'm Not a permanent resident of.
As it stands. They Refuse to rectify it, and I Refuse to use the cooker (That is also awaiting replacement too, as previous residents Both Human & Rodent. Neglected to care for the appliance. . .)
_ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ __ _ _ _
My hope, is that someone out there has come across this before, and can direct me to Any Requirements, Rules, etc so that I can force their hand into doing this remedial work. . .
Somewhere in my mind, I seem to recall that Certain Properties (Hospitals, Care homes, rentals, etc)are required to keep Electrical [and Gas] systems upto date with the current regulations. But I cannot find this information at this time :/
Thanks Gals & Guys