Hi
I'm trying to work out what order to do the various tasks involved in refitting our bathroom. I want to remove and replace a bath, sink on pedestal, shower tray and enclosure, replace electric shower with a thermostatic mixer, remove and replace all wall tiles, get upper walls and ceiling skimmed and tile the floor.
Oh and install spotlights and a shower light with extractor fan, so not much to do really
Before you ask, I'm only planning on doing the stripping out myself, and getting tradesmen in to do the rest, but I don't want to pay a middle man lots to subcontract it all if I can help it
Obviously stripping everything out, chasing wall to install new plumbing for the shower , and making good the wall ready for tiling comes first.
Then I'm guessing it would be fit new bath and shower tray?
And then tiling - on to shower tray and bath?
Then install sink [onto part tiled wall] and fit shower enclosure and recessed shower valve and rail onto tiles?
Then skim upper walls and ceiling and installing lighting, and finally put down plywood and tile floor last of all?
What do you reckon - will that work?
I'm trying to work out what order to do the various tasks involved in refitting our bathroom. I want to remove and replace a bath, sink on pedestal, shower tray and enclosure, replace electric shower with a thermostatic mixer, remove and replace all wall tiles, get upper walls and ceiling skimmed and tile the floor.
Oh and install spotlights and a shower light with extractor fan, so not much to do really
Before you ask, I'm only planning on doing the stripping out myself, and getting tradesmen in to do the rest, but I don't want to pay a middle man lots to subcontract it all if I can help it
Obviously stripping everything out, chasing wall to install new plumbing for the shower , and making good the wall ready for tiling comes first.
Then I'm guessing it would be fit new bath and shower tray?
And then tiling - on to shower tray and bath?
Then install sink [onto part tiled wall] and fit shower enclosure and recessed shower valve and rail onto tiles?
Then skim upper walls and ceiling and installing lighting, and finally put down plywood and tile floor last of all?
What do you reckon - will that work?