Hi all
As part of a house rewire, I have installed a new supply to a garage. Fairly standard arrangement, MCB and RCD in house CU, SWA to garage, small CU with MCB's for socket and lights. Fine thus far, however how would you document the tests on the EIC? Is the sub main treated as a "final" circuit of the main CU, documented as such and the two final circuits in the garage documented on a separate EIC, with their own Ze and PFC/PSCC etc.
Thanks
Martin
As part of a house rewire, I have installed a new supply to a garage. Fairly standard arrangement, MCB and RCD in house CU, SWA to garage, small CU with MCB's for socket and lights. Fine thus far, however how would you document the tests on the EIC? Is the sub main treated as a "final" circuit of the main CU, documented as such and the two final circuits in the garage documented on a separate EIC, with their own Ze and PFC/PSCC etc.
Thanks
Martin