Hi,
I'm an "Adjoining Owner" under the Party Wall Act, and have an Agreed surveyor, with a Party Wall Award already drafted and agreed. The "Building Owner's" works are in progress.
Some damage has occurred to my building that requires remediation work.
The Building Owner has proposed a method for the remediation. I asked the Agreed Surveyor if he was happy with this, and his response was "Should be confirmed by the building owners engineer that whatever is being done meets with his approval".
The Agreed Surveyor's remit is to represent the interests of both the Building Owner and Adjoining Owner, but he has pushed the responsibility of approving the remediation method onto the Building Owner's engineer, who of course only represents the interests of the Building Owner.
My questions are:
1. Is it normal / correct that the Party Wall Surveyor does not approve the proposed remediation works, rather pushes that responsibility onto the Building Owner's engineer?
2. Aside from the boundaries of responsibility, would you normally / reasonably expect a Party Wall Surveyor to have knowledge of the details of remediation works (e.g. different methods for horizontal vs. vertical crack repair, etc.)?
I'm an "Adjoining Owner" under the Party Wall Act, and have an Agreed surveyor, with a Party Wall Award already drafted and agreed. The "Building Owner's" works are in progress.
Some damage has occurred to my building that requires remediation work.
The Building Owner has proposed a method for the remediation. I asked the Agreed Surveyor if he was happy with this, and his response was "Should be confirmed by the building owners engineer that whatever is being done meets with his approval".
The Agreed Surveyor's remit is to represent the interests of both the Building Owner and Adjoining Owner, but he has pushed the responsibility of approving the remediation method onto the Building Owner's engineer, who of course only represents the interests of the Building Owner.
My questions are:
1. Is it normal / correct that the Party Wall Surveyor does not approve the proposed remediation works, rather pushes that responsibility onto the Building Owner's engineer?
2. Aside from the boundaries of responsibility, would you normally / reasonably expect a Party Wall Surveyor to have knowledge of the details of remediation works (e.g. different methods for horizontal vs. vertical crack repair, etc.)?