Hi,
I have just built a new 3m x 4m extension and have fitted new trifold patio windows.
I have fitted insulated cavity closures with integrated DPC on the sides.
My question is i have a stepped DPC on the floor so i am left with a gap between the floor insulation and the door frame.
What do i do with it?
I have underfloor heating pipes in the main floor screed, 50mm vertical floor insulation, which means the Concreet screed is approximatley 120mm away from the door frame.
Thanks