Hi,
Just got our engineers report back!!! so now were over £2000 down the road with architect, soil test and engineers report we find we need piling. 4000 x 4000 single storey extension flat roof three walls, 1 x window and double French doors. On clay but not a flood plain, no cracks in existing bricks or mortar. Our house isn't piled nor any neighbours nor the neighbours extension so why does our extension need piles?
Have regulations tightened up that much?
Are engineers covering their back sides these days?
The calculations have been sent to building control so is this final?
Is there a cheaper way?
Big question is how much does it cost to pile?
we were quoted £2,800 for standard footings, moving soil from site, inc digger hire. We now need 4 piles not sure how deep but I understand they are priced per metre.
thanks in advance of any answers.
Kind Regards
Terry
Just got our engineers report back!!! so now were over £2000 down the road with architect, soil test and engineers report we find we need piling. 4000 x 4000 single storey extension flat roof three walls, 1 x window and double French doors. On clay but not a flood plain, no cracks in existing bricks or mortar. Our house isn't piled nor any neighbours nor the neighbours extension so why does our extension need piles?
Have regulations tightened up that much?
Are engineers covering their back sides these days?
The calculations have been sent to building control so is this final?
Is there a cheaper way?
Big question is how much does it cost to pile?
we were quoted £2,800 for standard footings, moving soil from site, inc digger hire. We now need 4 piles not sure how deep but I understand they are priced per metre.
thanks in advance of any answers.
Kind Regards
Terry