I am about to begin plumbing an extension and could do with a bit of advice on two points:
1) The existing central heating is an 8/10mm microbore system running to all radiators from a single manifold, which is fed from the boiler by 22mm pipe. I have replaced and re-sited the boiler (W/Bosch Greenstar 42i combi) and wish to add the following in addition to the existing microbore manifold via a new 22mm loop:
a) A downstairs under floor heating manifold
b) An upstairs under floor heating manifold
c) A towel radiator
d) A standard radiator
I intend to feed the two new radiators using 15mm spurs leading from the 22mm main loop.
My concern is with mixing all of these different types of elements on a single 22mm CH loop and some of them not getting the flow that they need - particulary the microbore manifold as it will be the last item in the loop - any thoughts?
Also, I intend to make the 15mm spurs to one of the radiators roughly 3-4 metres long in order to keep the main 22mm loop as short as possible - does anyone foresee any problems with this?
2) My second point relates to the rising main. I have installed a new 25mm MDPE main pipe and would like some advice on when to slim it down to 15mm. I want to get as good a head of pressure into the boiler (and the various kitchen/bathroom taps) as possible, so would it be best to use a 25mm to 22mm stop cock and then run 22mm as close as possible to the boiler and the kitchen/bathrooms before converting down to 15mm for the last stretch? - or is this not the done thing?
Your advice would be most welcome
Many thanks in advance
Steve
1) The existing central heating is an 8/10mm microbore system running to all radiators from a single manifold, which is fed from the boiler by 22mm pipe. I have replaced and re-sited the boiler (W/Bosch Greenstar 42i combi) and wish to add the following in addition to the existing microbore manifold via a new 22mm loop:
a) A downstairs under floor heating manifold
b) An upstairs under floor heating manifold
c) A towel radiator
d) A standard radiator
I intend to feed the two new radiators using 15mm spurs leading from the 22mm main loop.
My concern is with mixing all of these different types of elements on a single 22mm CH loop and some of them not getting the flow that they need - particulary the microbore manifold as it will be the last item in the loop - any thoughts?
Also, I intend to make the 15mm spurs to one of the radiators roughly 3-4 metres long in order to keep the main 22mm loop as short as possible - does anyone foresee any problems with this?
2) My second point relates to the rising main. I have installed a new 25mm MDPE main pipe and would like some advice on when to slim it down to 15mm. I want to get as good a head of pressure into the boiler (and the various kitchen/bathroom taps) as possible, so would it be best to use a 25mm to 22mm stop cock and then run 22mm as close as possible to the boiler and the kitchen/bathrooms before converting down to 15mm for the last stretch? - or is this not the done thing?
Your advice would be most welcome
Many thanks in advance
Steve