Doing a single storey extension with steel ridge beam, high collar and bifolds in gable with steel RSJ spanning opening of 3600 it's 203x102 with 6mm 250mm wide plate welded on underside to carry outer gable brick leaf (projects 275mm so mortars in okay). Inner leaf carrying medium density blockwork. The ridge rsj is 178 x 102 and roof pitch is 18 degrees so will have marley moderns as tiles.
External dimensions are length 6000 and 5850 wide. Calcs are borrowed if you like from other similar spec jobs, architect friend supplied them and I know the properties they were taken from, one in my street, an identical house and extension to mine for the ridge beam, just my opening was 3600 and theirs was 3000 so from another job of same design with a 3600 opening the 203x102 with 6mm plate had been specified.
SO It looks to me like the steel or more likely the welded plate was already or probably has since twisted in the middle as the gable has gone up and the load increased. The plate is level either end by the padstones but has tilted downwards a little in the centre towards the outside by about 10mm. Sort of a twist as I describe it. This means left to right there will be a 10mm bow effectively in the opening.
Maybe I'm being overly concerned about 10mm, but looking at bi folds for the opening and want them to work okay without binding. No more load will be going on the outer brick skin but the roof tiles are yet to go on. However The rafters were over specified at 200mm (150 would have done) and I'm thinking the loadings are multi directional with ridge beam carring a bit, the rafters are butted together as well as birdsmouthed into the bolted plate on the steel so force into each other for a load pushing against each other and load is transferred down onto the walls more than the gable really.
Has anyone seen or suffered similar issues or got any sensible advice as . I'm not going to be able to blame anyone for any of this other than myself as Im managing the job. IS there a remedial option other than tearing it down or am I over worrying about it, I'm a bit picky about the accuracy at times but then the carpenter said the walls were 30mm out of parallel when doing the roof and I thought he was being picky! I'm doing this myself albeit with qualified tradesman, I dug the footings with a chap I know, I drove the dumper he did the digging and we poured the slab after brickwork done up to damp all to specifications and with full building control approval. I've had professional brickie crew in at weekends who work in the week on main large housing developments and the roof was constructed by a professional carpenter who happens to live in our road.
Any reassurances welcomed as I'm about to felt up the roof and either have a go at that or more likely get a roofer in!
Thanks
Mark
External dimensions are length 6000 and 5850 wide. Calcs are borrowed if you like from other similar spec jobs, architect friend supplied them and I know the properties they were taken from, one in my street, an identical house and extension to mine for the ridge beam, just my opening was 3600 and theirs was 3000 so from another job of same design with a 3600 opening the 203x102 with 6mm plate had been specified.
SO It looks to me like the steel or more likely the welded plate was already or probably has since twisted in the middle as the gable has gone up and the load increased. The plate is level either end by the padstones but has tilted downwards a little in the centre towards the outside by about 10mm. Sort of a twist as I describe it. This means left to right there will be a 10mm bow effectively in the opening.
Maybe I'm being overly concerned about 10mm, but looking at bi folds for the opening and want them to work okay without binding. No more load will be going on the outer brick skin but the roof tiles are yet to go on. However The rafters were over specified at 200mm (150 would have done) and I'm thinking the loadings are multi directional with ridge beam carring a bit, the rafters are butted together as well as birdsmouthed into the bolted plate on the steel so force into each other for a load pushing against each other and load is transferred down onto the walls more than the gable really.
Has anyone seen or suffered similar issues or got any sensible advice as . I'm not going to be able to blame anyone for any of this other than myself as Im managing the job. IS there a remedial option other than tearing it down or am I over worrying about it, I'm a bit picky about the accuracy at times but then the carpenter said the walls were 30mm out of parallel when doing the roof and I thought he was being picky! I'm doing this myself albeit with qualified tradesman, I dug the footings with a chap I know, I drove the dumper he did the digging and we poured the slab after brickwork done up to damp all to specifications and with full building control approval. I've had professional brickie crew in at weekends who work in the week on main large housing developments and the roof was constructed by a professional carpenter who happens to live in our road.
Any reassurances welcomed as I'm about to felt up the roof and either have a go at that or more likely get a roofer in!
Thanks
Mark
Last edited: