Now my experience of repairing large transformers is limited to just one repair to a 150 kW oil filled one. It provided the HT supplies to the 100 kW transmitter when I worked in Doha Qatar!
And that was just to help the Pakistani engineer in the SW transmitting station. And on the basis that he had the man power to remove the cover and drain the oil out!
Now that one was overheating to about 80 C as a result of arcing on the tap changer switch. I showed him how to file the contacts clean!
Now the substation transformer might be about 250 kVA. But residents told of a huge explosion from it. Most I have seen have a thermal cooling oil circulation to an elevated cooling tank well above the transformer.
Now clearly the transformer oil was well alight!
So how might it have overheated so much that it presumably boiled and vented to the outside where it caught fire?
Usually an important load like Heathrow would have two seperate 11 kV feeds and often with an automatic changeover!
The BBC Droitwich 400 kW transmitter takes a load of about 900 KVA and has two seperate 11 KV feeds which were manually switched in the rare event that the one being used failed. Since I worked there they may have had an automatic changeover fitted.
In the very rare event that both supplies failed then they had four 100 KVA generators available to be manually started with compressed air and put on load.
But at Bilsdale I think the single gas turbine was an automatic change over. They fitted that because a second source 11 KV supply was not available. It was about 1 MW and based on an RR jet engine similar to an RB211. You could stand close to it and talk to each other!
So where might I be able to read the report on the failures in due course?
And that was just to help the Pakistani engineer in the SW transmitting station. And on the basis that he had the man power to remove the cover and drain the oil out!
Now that one was overheating to about 80 C as a result of arcing on the tap changer switch. I showed him how to file the contacts clean!
Now the substation transformer might be about 250 kVA. But residents told of a huge explosion from it. Most I have seen have a thermal cooling oil circulation to an elevated cooling tank well above the transformer.
Now clearly the transformer oil was well alight!
So how might it have overheated so much that it presumably boiled and vented to the outside where it caught fire?
Usually an important load like Heathrow would have two seperate 11 kV feeds and often with an automatic changeover!
The BBC Droitwich 400 kW transmitter takes a load of about 900 KVA and has two seperate 11 KV feeds which were manually switched in the rare event that the one being used failed. Since I worked there they may have had an automatic changeover fitted.
In the very rare event that both supplies failed then they had four 100 KVA generators available to be manually started with compressed air and put on load.
But at Bilsdale I think the single gas turbine was an automatic change over. They fitted that because a second source 11 KV supply was not available. It was about 1 MW and based on an RR jet engine similar to an RB211. You could stand close to it and talk to each other!
So where might I be able to read the report on the failures in due course?
Last edited: