Regs question

Joined
31 Mar 2006
Messages
20,028
Reaction score
1,393
Location
Leeds
Country
United Kingdom
Hello

According to BS7671:2018, which one of the following tests does NOT need to be carried out in a specific order, in relation to other tests, during an initial verification?

A. Insulation Resistance
B. Continuity of conductors
C. Protection by SELV
D. Earth fault loop impedance.
 
Sponsored Links
Read reg 643.1 The tests of regs 643.2 to 643.6 shall be carried out in order
Therefore B A and C in that order are within that range
D is reg 643,7,3 therefore out that range
 
Perfect thank you very much. I’ve had my head in the regs for too long and couldn’t see what was right in front of me
 
Sponsored Links

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top