Hi there,
Quick question - I am having some work done in my house.
Building Inspector came out last week and said he wasn't 100% happy and requested some other work doing as per engineers calculations.
Builder was fine and did this work no issues. He took photographs, submitted these to the BI then carried on with the work. Plasterboard up and skimmed the walls.
Job has now finished and he is requesting payment. I paid 50% of the total before he even started and I am now suggesting I pay a further 25% as he has finished, but withhold the final 25% until the building inspector is happy with the work. Builder put up the plasterboard and skimmed before getting final approval.
So question to the professional builders on here. If you were my builder would be unhappy for your customer to withhold 25% until all is approved?
Quick question - I am having some work done in my house.
Building Inspector came out last week and said he wasn't 100% happy and requested some other work doing as per engineers calculations.
Builder was fine and did this work no issues. He took photographs, submitted these to the BI then carried on with the work. Plasterboard up and skimmed the walls.
Job has now finished and he is requesting payment. I paid 50% of the total before he even started and I am now suggesting I pay a further 25% as he has finished, but withhold the final 25% until the building inspector is happy with the work. Builder put up the plasterboard and skimmed before getting final approval.
So question to the professional builders on here. If you were my builder would be unhappy for your customer to withhold 25% until all is approved?