Two slow leaks have led to a saturated chipboard subfloor in our kitchen extension, as well as destroying the engineered wood floor. We noticed water leaking out through the walls at the DPC.
Construction of the floor is
Concrete slab
Thin blue membrane, visqueen
Thick black membrane, DPM? Turned up at the edges, and taken right up wall on the sink side
50mm celotex, foil covered
22mm chipboard, glued tg joints
Thin polystyrene ball plastic sandwich layer
Engineered floor.
The floor extends under the kitchen cabinets. Kitchen is galley layout.
The walls are
Plasterboard
Plastic membrane
Wood studs, fibreglass between.
The plasterboard had been set down into the concrete and although the membrane is between the two, damp had wicked up the board. It has not fallen apart and appears to be OK. I believe a gap ought to be left between the concrete and the plasterboard to prevent such wicking.
So far I have removed the floor down to DPC in accessible areas and from under one side's cabinets, the wet side. I have left the insulation and chipboard under the drier side, with the cut being approximately where the kickboard will sit. I have folded back the DPC and visqueen where accessible to allow the slab to dry, allow it doesn't seem wet and there is no condensation underneath where it remains in place.
The chipboard is sodden, and between the DPC and insulation there is a small amount of water trapped. I'm running a dehumidifier 24/7.
I have also cut a gap in the plasterboard approx 100mm from the floor, but cannot access all the plasterboard due to the cabinets, and because the DPC is taken up the wall on the sink side of the kitchen. I hope not to remove the cabinets. I have removed their bases to help take the flooring out.
My questions are,
1. Can I leave the insulation and chipboard in situ under the cabinets on one side? This would result in a butt joint between the old and new chipboard floor, which concerns me. It means the floating floor would but be continuous.
2. Should I cut the DPC which is running up the wall on the sink side to countertop level, to allow me to cut my plasterboard gap? Is it serving a purpose or required? To what length would you go to create this gap in inaccessible areas?
3. The horizontal foot piece of the studwork has been damp. I think it cannot be removed without redoing the walls which I'd like to avoid. Is there a treatment I can apply to stabilise and prevent further rot?
4. Can I safely reuse the insulation where it is in reasonable condition?
Construction of the floor is
Concrete slab
Thin blue membrane, visqueen
Thick black membrane, DPM? Turned up at the edges, and taken right up wall on the sink side
50mm celotex, foil covered
22mm chipboard, glued tg joints
Thin polystyrene ball plastic sandwich layer
Engineered floor.
The floor extends under the kitchen cabinets. Kitchen is galley layout.
The walls are
Plasterboard
Plastic membrane
Wood studs, fibreglass between.
The plasterboard had been set down into the concrete and although the membrane is between the two, damp had wicked up the board. It has not fallen apart and appears to be OK. I believe a gap ought to be left between the concrete and the plasterboard to prevent such wicking.
So far I have removed the floor down to DPC in accessible areas and from under one side's cabinets, the wet side. I have left the insulation and chipboard under the drier side, with the cut being approximately where the kickboard will sit. I have folded back the DPC and visqueen where accessible to allow the slab to dry, allow it doesn't seem wet and there is no condensation underneath where it remains in place.
The chipboard is sodden, and between the DPC and insulation there is a small amount of water trapped. I'm running a dehumidifier 24/7.
I have also cut a gap in the plasterboard approx 100mm from the floor, but cannot access all the plasterboard due to the cabinets, and because the DPC is taken up the wall on the sink side of the kitchen. I hope not to remove the cabinets. I have removed their bases to help take the flooring out.
My questions are,
1. Can I leave the insulation and chipboard in situ under the cabinets on one side? This would result in a butt joint between the old and new chipboard floor, which concerns me. It means the floating floor would but be continuous.
2. Should I cut the DPC which is running up the wall on the sink side to countertop level, to allow me to cut my plasterboard gap? Is it serving a purpose or required? To what length would you go to create this gap in inaccessible areas?
3. The horizontal foot piece of the studwork has been damp. I think it cannot be removed without redoing the walls which I'd like to avoid. Is there a treatment I can apply to stabilise and prevent further rot?
4. Can I safely reuse the insulation where it is in reasonable condition?