I've had to chop away a section of screeded floor (about 4m x 15cm) to reroute some pipe work and now have to repair it. The thickness of the screed floor varies from 4 to 7 cm.
I need the to be floor ready in about 25 days but realise you normally allow 1 day per 1 mm drying time. The final floor will have 10mm of SLC added to it.
So my questions are:
1. Is there an admixture I could use to speed up the drying process?
2. Would I be better off using a fast setting concrete?
Thanks for any help
Cheers
S
I've had to chop away a section of screeded floor (about 4m x 15cm) to reroute some pipe work and now have to repair it. The thickness of the screed floor varies from 4 to 7 cm.
I need the to be floor ready in about 25 days but realise you normally allow 1 day per 1 mm drying time. The final floor will have 10mm of SLC added to it.
So my questions are:
1. Is there an admixture I could use to speed up the drying process?
2. Would I be better off using a fast setting concrete?
Thanks for any help
Cheers
S