Repairing screed floor

Joined
27 Feb 2011
Messages
45
Reaction score
1
Location
Essex
Country
United Kingdom
Hi
I've had to chop away a section of screeded floor (about 4m x 15cm) to reroute some pipe work and now have to repair it. The thickness of the screed floor varies from 4 to 7 cm.

I need the to be floor ready in about 25 days but realise you normally allow 1 day per 1 mm drying time. The final floor will have 10mm of SLC added to it.

So my questions are:

1. Is there an admixture I could use to speed up the drying process?
2. Would I be better off using a fast setting concrete?

Thanks for any help
Cheers
S
 
Sponsored Links

DIYnot Local

Staff member

If you need to find a tradesperson to get your job done, please try our local search below, or if you are doing it yourself you can find suppliers local to you.

Select the supplier or trade you require, enter your location to begin your search.


Are you a trade or supplier? You can create your listing free at DIYnot Local

 
Back
Top