Hi.
I have started a DIY project to level my sloping law into two flat tiers with a retaining wall and have very little landscaping experience (but have been doing a lot of research) . I think I am mostly understood on the drainage requirements behind the wall but I have been reading mixed things about the footing requirements.
The wall is holding back about 600mm of earth, we have a heavy clay soil, and I am planning to build using a single layer of 7N bricks (so that the wall is 225mm thick).
Where I am at currently with the base requirements is that I think I need to dig a trench around 300m deep and 450mm wide. Then pour C20 mix concrete to 150mm thickness, then add courses of 7N bricks on top. I'd appreciate any advice on whether the depth and the thickness of the footing is reasonable and also whether I need to add a sub base to the footing or whether pouring on top if the heavy clay is sufficient?
Thanks in advance!
Chris
I have started a DIY project to level my sloping law into two flat tiers with a retaining wall and have very little landscaping experience (but have been doing a lot of research) . I think I am mostly understood on the drainage requirements behind the wall but I have been reading mixed things about the footing requirements.
The wall is holding back about 600mm of earth, we have a heavy clay soil, and I am planning to build using a single layer of 7N bricks (so that the wall is 225mm thick).
Where I am at currently with the base requirements is that I think I need to dig a trench around 300m deep and 450mm wide. Then pour C20 mix concrete to 150mm thickness, then add courses of 7N bricks on top. I'd appreciate any advice on whether the depth and the thickness of the footing is reasonable and also whether I need to add a sub base to the footing or whether pouring on top if the heavy clay is sufficient?
Thanks in advance!
Chris