I have the ground floor ceilings down. Should I run 15mm plastic central heating pipes just under the floorboards or should I run them through the centre of joists at 400mm centres? I found this summary elsewhere:
- Holes should be no greater than 0.25 of the depth of the joist.
Holes should be drilled at the neutral axis.
Holes should not be less than 3 diameters (centre to centre) apart.
Holes should be located between 0.25 and 0.4 times the span from the support.